Operating · Asia-Pacific
AirTrunk TOK1
Inzai, Chiba, Japan
- Full build
- 300 MW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- Multi-tenant
- Built by
- AirTrunk
- Investment
- not stated
- Investors
- Power
- Multiple 66 kV feeds, per AirTrunk.
- Timing
- Open. AirTrunk lists a campus of several buildings with a total capacity of more than 300 MW; it does not state how much is running.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- A hyperscale cloud campus in the Tokyo market's main data center district; recorded for market coverage, not as an AI training site.
- Note
- AirTrunk gives the figure as 300+ MW and does not state what it counts. The site is 13.25 hectares with a design PUE of 1.15, per the same page. The pin marks Inzai's data center district, not the surveyed site.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- AirTrunk — TOK1 campus page · companyPublished: not distinguished · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24 · Legacy source/access date: 2026-11-24
What changed
No changes recorded since November 24, 2026.
First recorded on November 24, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.