Under construction · Asia-Pacific
CDC Marsden Park
Marsden Park, New South Wales, Australia
- Full build
- 504 MW (IT power)
- Reported operating
- 0 MW (IT power)
- For
- Multi-tenant
- Built by
- CDC Data Centres
- Investment
- not stated
- Investors
- Power
- Not stated in the sources read.
- Timing
- CDC held its sod-turning on October 25, 2024. The New South Wales government approved the campus on November 28, 2025.
- Jobs
- Construction: more than 10,000 jobs from the development (CDC; construction and permanent not separated).
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- Planned as the largest data center campus in the Southern Hemisphere, per CDC; recorded for market coverage of Sydney.
- Note
- CDC states 504 MW of planned ICT capacity, with room to scale toward one gigawatt. The approval covers six four-story buildings on about 20 hectares and was reported as an AUD 3.1 billion development; no US dollar figure is recorded. The pin marks Marsden Park, not the surveyed site.
Evidence and delivery dependencies
- Metric-level verification not recorded
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- CDC Data Centres — CDC breaks ground on new data centre development in Marsden Park Industrial Precinct · companyPublished: 2024-10-25 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
- w.media — NSW govt approves CDC's 504 MW campus in Sydney · reportingPublished: 2025-11-28 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
What changed
No changes recorded since November 24, 2026.
First recorded on November 24, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.