    CoreWeave Muskogee OK

    Reported figures, sources and what changed.

    Under construction · North America

    CoreWeave Muskogee OK

    Muskogee, Oklahoma, United States

    Full build
    153 MW (IT power)
    Reported operating
    0 MW (IT power)
    For
    CoreWeave
    Built by
    CoreWeave
    Investment
    not stated
    Investors
    Power
    Not reported.
    Timing
    Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, June 13, 2026: "Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators." Epoch AI projects 153 MW of IT power by December 2027.
    Jobs
    not stated
    Community
    not stated
    Contested
    not recorded in this snapshot; absence is not evidence of no dispute
    AI tie
    Chip types Epoch AI lists: B300. Epoch AI names OpenAI as a speculative user.
    Record type
    Third-party estimate from Epoch AI (CC BY). Not read from an operator's own statement.
    Note
    Third-party estimate. Epoch AI reads IT power from satellite imagery, permits and public documents; the operator has not confirmed these figures. Epoch AI's confidence: OpenAI as user is marked speculative.

    Evidence and delivery dependencies

    • Metric-level verification not recorded

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    No changes recorded since November 20, 2026.

    First recorded on November 20, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.