Under construction · Asia-Pacific
Data Center Valley, Ekibastuz
Pavlodar Region, Kazakhstan
- Full build
- 1 GW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- Kazakhstan Ministry of AI and Digital Development
- Built by
- Kazakhtelecom
- Investment
- not stated
- Investors
- Government of Kazakhstan
- Power
- Ekibastuz is Kazakhstan's coal-power hub.
- Timing
- First facility due in the first half of 2027. Reports give its size as 50 MW or 125 MW.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- A state-led gigawatt campus selling cheap power to AI tenants.
- Note
- The 1 GW figure is a long-term target, not capacity under construction. The two first-phase sizes come from different government statements in mid-2026.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Interfax — Kazakhstan to commission 125 MW Ekibastuz data center in first half of 2027 · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-06-26
- W.Media — Data Center Valley on track to complete first 50 MW facility in June 2027 · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-08-01
What changed
- Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.
This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.