Under construction · North America
Project Matador
Carson County, Texas, United States
- Full build
- not stated (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- TensorWave (first lease)
- Built by
- Fermi America
- Investment
- not stated
- Investors
- Power
- Private on-site generation. Fermi says about 6 gigawatts of a planned 17 gigawatts is permitted, with first power targeted for 2026.
- Timing
- Fermi signed its first binding lease on August 10, 2026: a facility with 222 MW of total facility power for TensorWave, delivered in phases from the second half of 2027.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- TensorWave plans tens of thousands of AMD Instinct GPUs for AI training and inference in the leased facility.
- Note
- No full-build campus load is recorded. The 17 gigawatts is the developer's power generation plan, not a data center load, and the only contracted figure is the 222 MW lease. Fermi says the lease is worth about $6.5 billion over its first 15 years, with rights to two more facilities that would take the total above 650 MW, and that it has invested more than $1.5 billion so far. All figures are the company's own. The pin marks the Carson County site area northeast of Amarillo, not a surveyed point.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Fermi America — Fermi announces binding lease agreement with TensorWave · companyPublished: 2026-08-10 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
What changed
No changes recorded since November 24, 2026.
First recorded on November 24, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.