Under construction · North America
Google Cedar Rapids
Cedar Rapids, Iowa, United States
- Full build
- 261 MW (IT power)
- Reported operating
- 0 MW (IT power)
- For
- Built by
- Investment
- not stated
- Investors
- Power
- Not reported.
- Timing
- Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, April 16, 2026: "Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction." Epoch AI projects 261 MW of IT power by May 2027.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- Epoch AI tracks this site as an AI data center and lists no chip type. Epoch AI names Google DeepMind as a speculative user.
- Record type
- Third-party estimate from Epoch AI (CC BY). Not read from an operator's own statement.
- Note
- Third-party estimate. Epoch AI reads IT power from satellite imagery, permits and public documents; the operator has not confirmed these figures. Epoch AI's confidence: Google DeepMind as user is marked speculative.
Evidence and delivery dependencies
- Metric-level verification not recorded
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Epoch AI — Google Cedar Rapids (site page, latest entry 2026-04-16) · Third-party estimatePublished: not distinguished · Effective: not specified · Source checked: 2026-11-20 · Next review: 2026-12-20 · Legacy source/access date: 2026-04-16
What changed
No changes recorded since November 20, 2026.
First recorded on November 20, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.