    Google AI Hub Visakhapatnam

    Reported figures, sources and what changed.

    Under construction · Asia-Pacific

    Google AI Hub Visakhapatnam

    Visakhapatnam, Andhra Pradesh, India

    Full build
    1 GW (basis not stated)
    Reported operating
    not stated (basis not stated)
    For
    Google
    Built by
    AdaniConneX · Nxtra by Airtel
    Investment
    $15 billion (as reported)
    Investors
    Google · Adani Enterprises · Bharti Airtel
    Power
    Adani's renewable portfolio is the stated supply; an international subsea cable landing is part of the plan.
    Timing
    Groundbreaking 28 April 2026; the $15 billion runs 2026–2030.
    Jobs
    not stated
    Community
    Google's largest investment in India; a new subsea gateway for the east coast.
    Contested
    • A legal challenge over land sought to halt construction in August 2026 and failed (single secondary source).
    AI tie
    Google's first gigawatt-scale AI hub outside the US.

    Evidence and delivery dependencies

    • Metric-level verification not recorded
    • Full-build power basis not stated

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    1. Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.

    This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.