Operating · Europe
Google Waltham Cross
Waltham Cross, England, United Kingdom
- Full build
- 88 MW (IT power)
- Reported operating
- 88 MW (IT power)
- For
- Built by
- Investment
- not stated
- Investors
- Power
- Energy companies Epoch AI names: Shell Energy Europe and Engie. Fuel and contract terms are not reported there.
- Timing
- Epoch AI dates the first capacity to September 2025. Epoch AI's latest entry, April 23, 2026: "Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image; no capacity change since September 2025."
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- Chip types Epoch AI lists: TPU v6e. Epoch AI names Google DeepMind as a speculative user.
- Record type
- Third-party estimate from Epoch AI (CC BY). Not read from an operator's own statement.
- Note
- Third-party estimate. Epoch AI reads IT power from satellite imagery, permits and public documents; the operator has not confirmed these figures. Epoch AI's confidence: Google DeepMind as user is marked speculative. Epoch AI estimates 124 MW of total facility power for the same date; the register keeps the IT power figure. Epoch AI models the capital cost to date at about $3.3 billion in 2025 dollars, calculated from IT power; it is not a stated investment.
Evidence and delivery dependencies
- Metric-level verification not recorded
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Epoch AI — Google Waltham Cross (site page, latest entry 2026-04-23) · Third-party estimatePublished: not distinguished · Effective: not specified · Source checked: 2026-11-20 · Next review: 2026-12-20 · Legacy source/access date: 2026-04-23
What changed
No changes recorded since November 20, 2026.
First recorded on November 20, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.