    Homer City Energy Campus

    Reported figures, sources and what changed.

    Under construction · North America

    Homer City Energy Campus

    Homer City, Pennsylvania, United States

    Full build
    4.5 GW (basis not stated)
    Reported operating
    not stated (basis not stated)
    For
    Not yet named
    Built by
    Homer City Redevelopment · Kiewit (EPC) · EQT (gas supply)
    Investment
    not stated
    Investors
    Knighthead Capital (reported)
    Power
    Seven gas generating units on the site of the former coal plant, 4.4–4.5 GW, supplied by EQT.
    Timing
    Construction began 2025.
    Jobs
    not stated
    Community
    Reuse of a retired coal site and its grid interconnection.
    Contested
    • The largest gas build for data centers in the PJM region, where the market monitor attributes $23.1 billion of capacity costs across three auctions to data center demand.
    AI tie
    Speculative power-first campus seeking an AI tenant.
    Note
    The 4.5 GW figure is the generation capacity, not a contracted IT load.

    Evidence and delivery dependencies

    • Metric-level verification not recorded
    • Full-build power basis not stated

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    1. Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.

    This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.

    Open Homer City Energy Campus on the map →