Under construction · North America
Homer City Energy Campus
Homer City, Pennsylvania, United States
- Full build
- 4.5 GW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- Not yet named
- Built by
- Homer City Redevelopment · Kiewit (EPC) · EQT (gas supply)
- Investment
- not stated
- Investors
- Knighthead Capital (reported)
- Power
- Seven gas generating units on the site of the former coal plant, 4.4–4.5 GW, supplied by EQT.
- Timing
- Construction began 2025.
- Jobs
- not stated
- Community
- Reuse of a retired coal site and its grid interconnection.
- Contested
- The largest gas build for data centers in the PJM region, where the market monitor attributes $23.1 billion of capacity costs across three auctions to data center demand.
- AI tie
- Speculative power-first campus seeking an AI tenant.
- Note
- The 4.5 GW figure is the generation capacity, not a contracted IT load.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- GE Vernova — Homer City Redevelopment and Kiewit announce gas-powered data center campus · companyPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2025-04-02
What changed
- Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.