    Meta Prometheus

    Reported figures, sources and what changed.

    Under construction · North America

    Meta Prometheus

    New Albany, Ohio, United States

    Full build
    1 GW (basis not stated)
    Reported operating
    not stated (basis not stated)
    For
    Meta
    Built by
    Meta · Williams (on-site gas)
    Investment
    not stated
    Investors
    Meta
    Power
    Behind-the-meter natural gas built with Williams; Meta's January 2026 Vistra and Oklo nuclear agreements are framed around this cluster.
    Timing
    Meta said it comes online in 2026; a "tents over buildings" design chosen for speed.
    Jobs
    not stated
    Community
    not stated
    Contested
    • Ohio's data center sales-tax exemptions cost the state $1.6 billion in 2025, eleven times the projection (see the policy register).
    AI tie
    Meta's first gigawatt-scale training cluster, named by Zuckerberg in July 2025.
    Note
    One source gives 1 GW scaling to 1.5 GW; the 1 GW figure is the one Meta stated.

    Evidence and delivery dependencies

    • Metric-level verification not recorded
    • Full-build power basis not stated

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    1. Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.

    This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.