    Microsoft Fairwater Atlanta

    Reported figures, sources and what changed.

    Operating · North America

    Microsoft Fairwater Atlanta

    Atlanta, Georgia, United States

    Full build
    not stated (basis not stated)
    Reported operating
    not stated (basis not stated)
    For
    Microsoft (OpenAI workloads)
    Built by
    Microsoft
    Investment
    not stated
    Investors
    Microsoft
    Power
    Grid; designed with no UPS or generator sets, ~140 kW per rack.
    Timing
    Online November 2025.
    Jobs
    not stated
    Community
    not stated
    Contested
    not recorded in this snapshot; absence is not evidence of no dispute
    AI tie
    Second node of the Fairwater AI WAN; hundreds of thousands of GB200 and GB300 GPUs.
    Note
    Microsoft has not stated a capacity for the Atlanta site.

    Evidence and delivery dependencies

    • Metric-level verification not recorded
    • Full-build power basis not stated

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    No changes recorded since October 16, 2026.

    This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.