Operating · Asia-Pacific
Microsoft India South Central region
Hyderabad, India
- Full build
- 600 MW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- Microsoft
- Built by
- Microsoft
- Investment
- not stated
- Investors
- Microsoft
- Power
- Not stated.
- Timing
- Generally available August 6, 2026, as Microsoft's fourth cloud region in India.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- Part of Microsoft's $3 billion India commitment.
- Note
- The 600 MW figure is from a tracker, not from Microsoft. Operating capacity is not stated.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
- The legacy mid-2026 go-live target has elapsed while the record remains under construction. Obtain a dated commissioning update; do not infer completion.
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- DCD — Microsoft launches India South Central cloud region in Hyderabad · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-08-06
- AI Data Center Index — facilities announced in 2026Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15
What changed
- Recorded : Status changed from under construction to operating. A source added to the record the same day (it may support a different field): DCD — Microsoft launches India South Central cloud region in Hyderabad, dated .
- Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.
This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.