Stalled or cut back · North America
Project Jade
Laramie County, Wyoming, United States
- Full build
- 1.8 GW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- Not named
- Built by
- Tallgrass · Crusoe (left the project)
- Investment
- not stated
- Investors
- Power
- Tallgrass is building the Cheyenne Power Hub, a natural gas plant dedicated to the campus in the Switchgrass Industrial Park.
- Timing
- Announced in July 2025. Crusoe disclosed on June 9, 2026 that it had paused development; the Wyoming Tribune Eagle reported the same day that it had left the site about two months earlier. Tallgrass said its own work continues.
- Jobs
- not stated
- Community
- not stated
- Contested
- Crusoe paused its development at its customer's request and left the site. The tenant has never been named.
- AI tie
- Planned as an AI campus that could scale to 10 gigawatts, which the developers said would make it the largest in the United States.
- Note
- The 1.8 gigawatts is the developers' announced first-phase figure; no source states what it counts. Recorded as stalled because the data center developer has left; the power plant work is reported as continuing. The pin marks the area south of Cheyenne, not a surveyed point.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Wyoming Tribune Eagle — Crusoe pulls out of Project Jade data center · reportingPublished: 2026-06-09 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
- Blockspace via Yahoo Finance — Crusoe pauses Wyoming data center build: Bloomberg · reportingPublished: 2026-06-10 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
What changed
No changes recorded since November 24, 2026.
First recorded on November 24, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.