    SK-AWS Ulsan AI data center

    Reported figures, sources and what changed.

    Under construction · Asia-Pacific

    SK-AWS Ulsan AI data center

    Ulsan, South Korea

    Full build
    100 MW (basis not stated)
    Reported operating
    0 MW (basis not stated)
    For
    Amazon Web Services
    Built by
    SK Group
    Investment
    $5.2 billion (as reported)
    Investors
    Power
    Not stated in the reports read.
    Timing
    Ground was broken on August 29, 2025. On November 21, 2026 the facility was reported 71% complete, with operations due in late 2027.
    Jobs
    not stated
    Community
    not stated
    Contested
    not recorded in this snapshot; absence is not evidence of no dispute
    AI tie
    Built for GPU-based high-density servers; reported as the first step in SK Group's wider AI data center plan.
    Note
    The investment is reported as 7 trillion won ($5.2 billion) through 2029. The Korea Times reported at the groundbreaking that 40 MW would open first and the rest follow within a year and a half. The pin marks Ulsan, not the surveyed site.

    Evidence and delivery dependencies

    • Metric-level verification not recorded
    • Full-build power basis not stated

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    No changes recorded since November 24, 2026.

    First recorded on November 24, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.