Under construction · Asia-Pacific
SK-AWS Ulsan AI data center
Ulsan, South Korea
- Full build
- 100 MW (basis not stated)
- Reported operating
- 0 MW (basis not stated)
- For
- Amazon Web Services
- Built by
- SK Group
- Investment
- $5.2 billion (as reported)
- Investors
- Power
- Not stated in the reports read.
- Timing
- Ground was broken on August 29, 2025. On November 21, 2026 the facility was reported 71% complete, with operations due in late 2027.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- Built for GPU-based high-density servers; reported as the first step in SK Group's wider AI data center plan.
- Note
- The investment is reported as 7 trillion won ($5.2 billion) through 2029. The Korea Times reported at the groundbreaking that 40 MW would open first and the rest follow within a year and a half. The pin marks Ulsan, not the surveyed site.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- The Korea Times — SK, AWS break ground for AI data center in Ulsan · reportingPublished: 2025-08-29 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
- Aju Press — South Korea presses with AI build-out despite jitters · reportingPublished: 2026-11-21 · Effective: not specified · Source checked: 2026-11-24 · Next review: 2026-12-24
What changed
No changes recorded since November 24, 2026.
First recorded on November 24, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.