    SoftBank Tomakomai AI data center

    Reported figures, sources and what changed.

    Under construction · Asia-Pacific

    SoftBank Tomakomai AI data center

    Tomakomai, Hokkaido, Japan

    Full build
    300 MW (basis not stated)
    Reported operating
    not stated (basis not stated)
    For
    SoftBank Corp.
    Built by
    SoftBank Corp.
    Investment
    not stated
    Investors
    SoftBank Corp.
    Power
    Hokkaido renewables are the stated pitch.
    Timing
    Under construction; SoftBank said in February 2026 that operations start in fiscal 2026, which ends March 31, 2027. The first phase is about 50 MW.
    Jobs
    not stated
    Community
    not stated
    Contested
    not recorded in this snapshot; absence is not evidence of no dispute
    AI tie
    Japan's sovereign AI compute, with NVIDIA.

    Evidence and delivery dependencies

    • Metric-level verification not recorded
    • Full-build power basis not stated

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    1. Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.