Under construction · Asia-Pacific
SoftBank Tomakomai AI data center
Tomakomai, Hokkaido, Japan
- Full build
- 300 MW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- SoftBank Corp.
- Built by
- SoftBank Corp.
- Investment
- not stated
- Investors
- SoftBank Corp.
- Power
- Hokkaido renewables are the stated pitch.
- Timing
- Under construction; SoftBank said in February 2026 that operations start in fiscal 2026, which ends March 31, 2027. The first phase is about 50 MW.
- Jobs
- not stated
- Community
- not stated
- Contested
- not recorded in this snapshot; absence is not evidence of no dispute
- AI tie
- Japan's sovereign AI compute, with NVIDIA.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- SoftBank News — Tomakomai AI data center interview · companyPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-02-25
- AI Data Center Index — facilities announced in 2026Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15
What changed
- Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.
This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.