Under construction · North America
Stargate Doña Ana (Project Jupiter)
Doña Ana County, New Mexico, United States
- Full build
- 2.2 GW (facility power)
- Reported operating
- 0 MW (facility power)
- For
- OpenAI (Oracle-operated)
- Built by
- STACK Infrastructure
- Investment
- not stated
- Investors
- STACK Infrastructure · Oracle (hardware)
- Power
- Grid; facility-power figure.
- Timing
- Construction had advanced well past foundations by June 22, 2026, with no building yet running. Epoch AI projects completion by the end of 2028.
- Jobs
- not stated
- Community
- not stated
- Contested
- The air permit for the on-site microgrid is still pending. On November 6, 2026 the hearing officer vacated the December 7 hearing and set no new date; the state and the developer had already waived the November 23 decision deadline. A status conference is set for November 19, and a new hearing waits on the state's revised recommendation.
- AI tie
- Stargate's largest projected single site.
- Note
- Epoch AI's site page projects 1,750 MW of IT power; the 2,200 MW figure here is facility power from its overview, a different basis. The developer's latest permit filing replaces gas turbines with fuel cells.
Evidence and delivery dependencies
Metrics: capacityMw, operatingMw, timing, power, status. Historical April snapshot. Epoch estimates total facility power, including conversions from IT power; projected completion is not a commissioning guarantee. Other record fields retain their original sources.
Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18- Source review overdue
- Historical evidence requires current status check
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Epoch AI — OpenAI Stargate: where the US sites stand · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18
- Epoch AI — OpenAI Stargate New Mexico (site timeline, latest entry 2026-06-22) · Third-party estimatePublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: 2026-12-12 · Legacy source/access date: 2026-06-22
- Albuquerque Journal — Project Jupiter air permit faces new delay · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-11-06
- KFOX — Project Jupiter air permit hearing postponed; no new date set · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-13 · Next review: not scheduled · Legacy source/access date: 2026-11-09
What changed
- Recorded : Recordkeeping: the register began recording what an operating figure counts (facility power). No reported figure changed.
This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.