    Reported figures, sources and what changed.

    Under construction · North America

    Stargate Lordstown

    Lordstown, Ohio, United States

    Full build
    not stated (facility power)
    Reported operating
    0 MW (facility power)
    For
    OpenAI (SoftBank-owned hardware)
    Built by
    SoftBank · Foxconn
    Investment
    not stated
    Investors
    SoftBank Group · Foxconn
    Power
    The former GM plant already has a substation connected.
    Timing
    Active construction with the roof mostly on by July 30, 2026, though no building was running. Epoch AI projects operation from March 2027.
    Jobs
    not stated
    Community
    not stated
    Contested
    not recorded in this snapshot; absence is not evidence of no dispute
    AI tie
    A SoftBank–Foxconn joint venture on the former GM Lordstown site; the smallest Stargate site at under 0.3 GW.
    Note
    Epoch AI's site page projects 214 MW of IT power; OpenAI's own statements imply about 300 MW. Neither is a company figure for this site, so the capacity is withheld from totals.

    Evidence and delivery dependencies

    Metrics: capacityMw, operatingMw, timing, power, status. Historical April snapshot. Epoch estimates total facility power, including conversions from IT power; projected completion is not a commissioning guarantee. Other record fields retain their original sources.

    Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18
    • Source review overdue
    • Historical evidence requires current status check
    • Epoch reports less than 300 MW, not an exact 300 MW. The exact capacity is withheld pending clarification; the source describes manufacturing activity and limited campus construction.

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    1. Recorded : Status changed from announced to under construction. A source added to the record the same day (it may support a different field): Epoch AI — OpenAI Stargate Lordstown (site timeline, latest entry 2026-07-30), dated .
    2. Recorded : Full-build capacity changed from 300 MW (facility power) to not reported. Latest source on the record at the time (it may not be the source of this change): Epoch AI — OpenAI Stargate: where the US sites stand, dated .Editor's note: The source gives an upper bound of less than 300 MW, not an exact figure. The exact value is withheld and the bound is kept in the record's notes: a bound is not converted to a measurement.
    3. Recorded : Recordkeeping: the register began recording what an operating figure counts (facility power). No reported figure changed.

    This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.