Under construction · Europe
Narvik AI gigafactory (ex-Stargate Norway)
Kvandal, Narvik, Norway
- Full build
- 230 MW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- Microsoft (replacing OpenAI)
- Built by
- Nscale · Aker ASA
- Investment
- $1 billion (as reported)
- Investors
- Aker ASA · Nscale
- Power
- 100% renewable (hydro) above the Arctic Circle.
- Timing
- First 230 MW phase targeted for H2 2026 (aggregator figure); Microsoft's 30,000 NVIDIA Rubin GPUs delivered in 2027; a 520 MW longer-term plan.
- Jobs
- not stated
- Community
- Cheap hydro and cold air; a sovereign-compute pitch for Europe.
- Contested
- OpenAI dropped its lease in April 2026 without a final contract; Microsoft took the capacity.
- AI tie
- Launched as Stargate Norway in 2025 with a 100,000-GPU ambition; now a Microsoft capacity contract.
- Note
- The $1 billion figure is the reported first-phase investment.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- CNBC — OpenAI pulls back from Stargate Norway as Microsoft takes overPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-15
- DCD — Microsoft contracts 30,000 Rubin GPUs from Nscale at NarvikPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-15
- TIME — Inside Nscale's data center above the Arctic CirclePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-06-03
What changed
- Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.
This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.