    Reported figures, sources and what changed.

    Under construction · North America

    Stargate Saline Township (The Barn)

    Saline Township, Michigan, United States

    Full build
    1.4 GW (facility power)
    Reported operating
    0 MW (facility power)
    For
    OpenAI (Oracle-operated)
    Built by
    Related Digital
    Investment
    not stated
    Investors
    Related Digital · Oracle (hardware)
    Power
    DTE Energy supplies the grid connection.
    Timing
    Groundwork for building 1 was visible by March 12, 2026. DTE Energy's maximum load is scheduled for December 2027 and can move out a year; Epoch AI projects the three buildings running by the end of 2028.
    Jobs
    not stated
    Community
    not stated
    Contested
    • The township board voted against rezoning in September 2025; the developer sued and the township settled in October 2025. A resident challenged the settlement in court in December 2025. In early 2026 a Washtenaw County judge denied her motion to intervene; her lawyer said the ruling can be appealed.
    AI tie
    The Stargate site that went through litigation to exist.
    Note
    Epoch AI's site page projects 988 MW of IT power and notes a state utility filing that gives 1,383 MW; the 1,400 MW figure here is facility power. Epoch's page lists the location as Benton, Michigan, which does not match the Saline Township reporting.

    Evidence and delivery dependencies

    Metrics: capacityMw, operatingMw, timing, power, status. Historical April snapshot. Epoch estimates total facility power, including conversions from IT power; projected completion is not a commissioning guarantee. Other record fields retain their original sources.

    Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18
    • Source review overdue
    • Historical evidence requires current status check

    Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.

    Sources

    What changed

    1. Recorded : Recordkeeping: the register began recording what an operating figure counts (facility power). No reported figure changed.

    This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.