Under construction · Middle East & Africa
Stargate UAE (UAE–US AI Campus)
Abu Dhabi, United Arab Emirates
- Full build
- 5 GW (basis not stated)
- Reported operating
- not stated (basis not stated)
- For
- OpenAI · G42
- Built by
- G42 · Khazna Data Centers
- Investment
- not stated
- Investors
- G42 · MGX · OpenAI · Oracle · NVIDIA · Cisco · SoftBank Group
- Power
- Not stated for the campus; the UAE grid is gas and nuclear (Barakah) backed.
- Timing
- First 200 MW of a 1 GW cluster due in 2026; the rest of the 1 GW and the 5 GW campus have no confirmed dates.
- Jobs
- not stated
- Community
- Sovereign AI capacity under the US–UAE chip export framework.
- Contested
- US export-control conditions on advanced chips govern what can be installed.
- AI tie
- The largest non-US Stargate; OpenAI's first sovereign deployment.
- Note
- The 5 GW is the campus plan; only the 200 MW first phase has a 2026 date.
Evidence and delivery dependencies
- Metric-level verification not recorded
- Full-build power basis not stated
Diligence sequence: power agreement → load connection → permits → equipment → building → fit-out → commissioning. Completion of each dependency is unverified unless the linked evidence explicitly establishes it.
Sources
- Gulf News — Stargate UAE first phase of 200MW to complete by 2026Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-10
- The Tech Capital — first 200MW of Stargate UAE online in 2026Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-20
What changed
- Recorded : Recordkeeping: an unstated operating figure that was stored as 0 now reads not reported. No reported figure changed.
This history begins on October 16, 2026. "Recorded" is the day a change was entered here, not the day it happened. Tracked: name, tenant, status, capacity and what it counts, and stated investment. Changes to other fields, such as sources, timing and power, are not listed.