    Koko's Data Center Eye View

    Selected AI infrastructure, explained for professional decisions: campuses, energy arrangements, evidence and delivery questions.

    View as

    Key numbers this month

    Updated November 24, 2026

    • $803 billion to $828 billion

      Five companies are on track to spend more than $800 billion on capex in 2026.

      Directional · After third-quarter 2026 results

    • 122 GW

      GE Vernova has 122 GW of gas turbines under contract, and new orders deliver years out.

      Reported · End of third quarter 2026

    • $96.5 billion

      US data center construction is running near $96 billion a year.

      Reported · September 2026, preliminary

    • 300+

      More than 300 US cities, towns and counties have paused or banned large data centers.

      Reported · July 2026

    See all core numbers, sources and what changed

    Curated coverage: 120 selected campuses and 17 energy assets or policies, not a census. Empty map areas do not mean no infrastructure. Snapshot 2026-11-12; individual source and review dates vary.

    Show me

    Showing 120 of 120 campuses (79 operating, 35 under construction, 4 planned, 1 announced, 1 stalled or cut back) and 17 of 17 energy records.

    Filter the evidence

    Campus filters affect map, register, comparisons and brief. Energy type filters energy records only; region and backer apply to both. Target dates filter cited projections, not historical operating status. Missing dated milestones are excluded when a date filter is active.

    The God's-eye view

    Campuses, energy arrangements and regional context

    Drag to move, pinch or Ctrl + scroll to zoom, or search. Clusters split as you close in; tap a pin for its record. The register below is the same data as a table.

    Find by place

    Counts are tracked records plus sites mapped in OpenStreetMap, not every data center in a place.Browse all countries and states

    Interactive map, centred near 0.0°N 0.0°E, zoom 1.0×. Arrow keys pan, plus and minus zoom, zero resets. Every place on the map is also in the register below.

    2,000 km

    0.0°N 0.0°E, zoom 1.0×

    Data center sites and energy assets, worldwide29235996524724322
    Map legend · full build
    • Operating
    • Under construction
    • Planned
    • Announced
    • Stalled or cut back

    Circles: campuses. Small rings: sites mapped in OpenStreetMap, not tracked. Diamonds: energy/policy. Hollow: unknown or equal sizing. Cluster numbers count places. Power bases vary; energy MW is not campus supply.

    Pick a circle (a campus) or a diamond (a plant, reactor or grid rule) on the map, or a row in the register below, to read its full record and sources. Read the vocabulary in How a Data Center Gets Built.
    OperatingUnder constructionPlannedAnnouncedStalled or cut backEnergy asset or grid policySeveral places; zoom in to splitCampus pin size: full build (mixed bases). Hollow pins mean unknown or equal sizing. Energy pins use reported asset/deal MW, not campus supply. Basemap: Natural Earth.

    2 selected energy records have undisclosed locations and appear only in the register. Regional policy markers are reference locations, not facility sites.

    World · campuses
    120
    Operating
    79
    Under construction
    35
    Planned
    4
    Announced
    1
    Stalled or cut back
    1

    AI infrastructure intelligence

    Your professional briefing

    What changed · October 18

    Koko now separates power bases, qualifies estimates and flags evidence gaps. These are editorial changes, not new campus commissioning reports.

    Inspect the change log

    Why it matters

    Capacity ambitions and delivery dates are different inputs to an AI investment case.

    What to investigate next

    Stress-test start dates, take-or-pay commitments and fallback capacity before approving spend.

    The briefing follows your selection, comparison or energy/grid mode. Decision tools use explicit scenario assumptions; campus MW is not imported as a price.

    Filtered register · 120 selected campuses

    facility power

    9.3 GW

    Full-build figures · 6/7 records sized

    Reported operating: 0 MW

    Operating basis recorded here for 6/120 selected records

    IT power

    24.1 GW

    Full-build figures · 85/85 records sized

    Reported operating: 10.8 GW

    Operating basis recorded here for 82/120 selected records

    basis not stated

    29.3 GW

    Full-build figures · 25/28 records sized

    Reported operating: 1.8 GW

    Operating basis recorded here for 5/120 selected records

    Snapshot 2026-11-12; metric dates vary. Full build includes projections and estimates, not demand or energy use. 4 exact full-build values unknown. Bases are not added together; no assumed PUE conversion. An operating campus can still have future phases.

    Global coverage · all selected records

    120 campuses · 17 energy assets and policies.

    Global register · 120 selected campuses

    facility power

    9.3 GW

    Full-build figures · 6/7 records sized

    Reported operating: 0 MW

    Operating basis recorded here for 6/120 selected records

    IT power

    24.1 GW

    Full-build figures · 85/85 records sized

    Reported operating: 10.8 GW

    Operating basis recorded here for 82/120 selected records

    basis not stated

    29.3 GW

    Full-build figures · 25/28 records sized

    Reported operating: 1.8 GW

    Operating basis recorded here for 5/120 selected records

    Snapshot 2026-11-12; metric dates vary. Full build includes projections and estimates, not demand or energy use. 4 exact full-build values unknown. Bases are not added together; no assumed PUE conversion. An operating campus can still have future phases.

    The register

    Selected campuses and energy records

    Snapshot 2026-11-12. Targets, reported operation and full build are different phases; sources and evidence gaps open with each record. Select a row to view its map detail.

    Browse 120 campuses and 17 energy records
    Sort by
    SiteForStatusFull buildOperatingPowerTiming
    Inzai, Chiba, Japan
    Multi-tenantOperating300 MW
    basis not stated
    not stated
    basis not stated
    Multiple 66 kV feeds, per AirTrunk.Open. AirTrunk lists a campus of several buildings with a total capacity of more than 300 MW; it does not state how much is running.
    Zhangbei County, Hebei, China
    AlibabaOperating169 MW
    IT power · Epoch AI estimate
    169 MW
    IT power
    Not reported.Epoch AI dates the first capacity to September 2025. Epoch AI's latest entry, January 3, 2026: "Expect Building 4-6 have finished upgrading with new chillers."
    Madison County, Mississippi, United States
    AmazonOperating683 MW
    IT power · Epoch AI estimate
    284 MW
    IT power
    Not reported.Epoch AI dates the first capacity to June 2025. Epoch AI's latest entry, June 4, 2026: "Buildings 6 and 7 roof completed." Epoch AI projects 683 MW of IT power by March 2028.
    New Carlisle, Indiana, United States
    Anthropic (on AWS)Operating2.2 GW
    basis not stated
    not stated
    basis not stated
    Grid (Indiana Michigan Power); outside-air cooling October to March per AWS.Operational October 2025 with 7 of ~30 planned buildings; 2.2 GW at full build.
    Ridgeland, Mississippi, United States
    AmazonOperating840 MW
    IT power · Epoch AI estimate
    228 MW
    IT power
    Energy companies Epoch AI names: Entergy. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to May 2026. Epoch AI's latest entry, May 15, 2026: "Buildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete." Epoch AI projects 840 MW of IT power by September 2028.
    Colorado City, Texas, United States
    AnthropicUnder construction207 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, July 30, 2026: "Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north." Epoch AI projects 207 MW of IT power by April 2027.
    Barker, New York, United States
    AnthropicOperating378 MW
    IT power · Epoch AI estimate
    210 MW
    IT power
    Not reported.Epoch AI dates the first capacity to May 2026. Epoch AI's latest entry, October 31, 2026: "Building 2 (AKA CB4) is operational." Epoch AI projects 378 MW of IT power by March 2027.
    Berwick, Pennsylvania, United States
    AmazonOperating169 MW
    IT power · Epoch AI estimate
    108 MW
    IT power
    Not reported.Epoch AI dates the first capacity to September 2025. Epoch AI's latest entry, August 1, 2026: "Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it." Epoch AI projects 169 MW of IT power by August 2027.
    New Albany, Ohio, United States
    AmazonOperating338 MW
    IT power · Epoch AI estimate
    213 MW
    IT power
    Not reported.Epoch AI dates the first capacity to December 2024. Epoch AI's latest entry, May 18, 2026: "Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimet." Epoch AI projects 338 MW of IT power by July 2027.
    Lima, Peru
    Amazon Web ServicesAnnounced40 MW
    basis not stated
    not stated
    basis not stated
    Not stated.Announced.
    Sedenak, Johor, Malaysia
    ByteDanceOperating243 MW
    IT power · Epoch AI estimate
    243 MW
    IT power
    Not reported.Epoch AI dates the first capacity to December 2022. Epoch AI's latest entry, September 13, 2026: "No visible construction work on Buildings 8-10, but no cars in their carparks either (whereas Building 7 has many cars)."
    Seine-et-Marne, France
    Mistral AI and othersPlanned1.4 GW
    basis not stated
    not stated
    basis not stated
    France's nuclear-heavy grid is the pitch.Construction was expected to begin in the second half of 2026, with operations by 2028. In June 2026 the partners set a wider goal of up to 3 GW across France.
    Marsden Park, New South Wales, Australia
    Multi-tenantUnder construction504 MW
    IT power
    0 MW
    IT power
    Not stated in the sources read.CDC held its sod-turning on October 25, 2024. The New South Wales government approved the campus on November 28, 2025.
    Memphis, Tennessee, United States
    AnthropicOperating340 MW
    IT power · Epoch AI estimate
    340 MW
    IT power
    Energy companies Epoch AI names: MLGW. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to August 2024. Epoch AI's latest entry, June 15, 2026: "No major changes to the data center since February."
    Barker, New York, United States
    G42Operating58 MW
    IT power · Epoch AI estimate
    58 MW
    IT power
    Not reported.Epoch AI dates the first capacity to October 2025. Epoch AI's latest entry, July 23, 2026: "Both buildings still operational according to satellite imagery."
    Chester, Virginia, United States
    CoreWeaveOperating113 MW
    IT power · Epoch AI estimate
    82 MW
    IT power
    Not reported.Epoch AI dates the first capacity to January 2024. Epoch AI's latest entry, May 20, 2026: "Based on satellite imagery, Building 3 has cleared its land and is beginning construction." Epoch AI projects 113 MW of IT power by June 2027.
    Dalton, Georgia, United States
    CoreWeaveOperating28 MW
    IT power · Epoch AI estimate
    28 MW
    IT power
    Not reported.Epoch AI dates the first capacity to February 2026. Epoch AI's latest entry, February 20, 2026: "Building 1 is operational, given it was announced completed 4 months ago and looks completed in satellite imagery."
    Denton, Texas, United States
    OpenAIOperating282 MW
    IT power · Epoch AI estimate
    262 MW
    IT power
    Not reported.Epoch AI dates the first capacity to May 2025. Epoch AI's latest entry, September 1, 2026: "Building 8 interior fit-out scheduled to begin." Epoch AI projects 282 MW of IT power by May 2027.
    Ellendale, North Dakota, United States
    CoreWeaveOperating400 MW
    IT power · Epoch AI estimate
    68 MW
    IT power
    Not reported.Epoch AI dates the first capacity to October 2025. Epoch AI's latest entry, June 30, 2026: "According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed." Epoch AI projects 400 MW of IT power by June 2027.
    Afton, Texas, United States
    CoreWeaveOperating528 MW
    IT power · Epoch AI estimate
    132 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2026. Epoch AI's latest entry, August 30, 2026: "Building 1 operational at full capacity." Epoch AI projects 528 MW of IT power by January 2029.
    Lancaster, Pennsylvania, United States
    CoreWeaveUnder construction92 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in June 2027. Epoch AI's latest entry, July 13, 2026: "Cooling install continues on the roof, satellite imagery indicates that not all units have been completed." Epoch AI projects 92 MW of IT power by June 2027.
    Marble, North Carolina, United States
    CoreWeaveOperating65 MW
    IT power · Epoch AI estimate
    65 MW
    IT power
    Not reported.Epoch AI dates the first capacity to March 2026. Epoch AI's latest entry, May 6, 2026: "Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online."
    Muskogee, Oklahoma, United States
    CoreWeaveUnder construction153 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, June 13, 2026: "Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators." Epoch AI projects 153 MW of IT power by December 2027.
    Øvrebø, Agder, Norway
    CoreWeaveOperating42 MW
    IT power · Epoch AI estimate
    42 MW
    IT power
    Not reported.Epoch AI dates the first capacity to July 2025. Epoch AI's latest entry, August 15, 2026: "Building 1 still operational."
    Abilene, Texas, United States
    MicrosoftUnder construction672 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in September 2027. Epoch AI's latest entry, January 15, 2026: "Land clearing continues." Epoch AI projects 672 MW of IT power by November 2027.
    Frankfurt, Hesse, Germany
    Multi-tenantUnder construction81 MW
    IT power
    not stated
    basis not stated
    CyrusOne says the campus runs on 100% renewable energy and can supply up to 40 MW of waste heat to the district's heating network.Ground was broken in July 2024 and the structure was topped out in February 2026. The first phase, 9 MW of IT capacity, was due in 2026.
    Pavlodar Region, Kazakhstan
    Kazakhstan Ministry of AI and Digital DevelopmentUnder construction1 GW
    basis not stated
    not stated
    basis not stated
    Ekibastuz is Kazakhstan's coal-power hub.First facility due in the first half of 2027. Reports give its size as 50 MW or 125 MW.
    Johor Bahru, Johor, Malaysia
    Not reportedOperating422 MW
    IT power · Epoch AI estimate
    422 MW
    IT power
    Not reported.Epoch AI dates the first capacity to January 2026. Epoch AI's latest entry, October 1, 2026: "Buildings 7-8 assumed operational."
    Iskandar Puteri, Johor, Malaysia
    Not reportedOperating473 MW
    IT power · Epoch AI estimate
    473 MW
    IT power
    Not reported.Epoch AI dates the first capacity to December 2024. Epoch AI's latest entry, October 2, 2026: "Buildings 7-10 are operational."
    Clondalkin, County Dublin, Ireland
    Not namedUnder construction90 MW
    IT power
    not stated
    basis not stated
    Not stated in the report read. New Dublin connections fall under the regulator's large energy user policy (see the Dublin connection policy record).Not stated in the report read.
    Borlänge, Dalarna, Sweden
    Mistral AIUnder construction48 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in June 2027. Epoch AI's latest entry, August 17, 2026: "Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed." Epoch AI projects 48 MW of IT power by June 2028.
    Ulanqab, Inner Mongolia, China
    Not reportedOperating470 MW
    IT power · Epoch AI estimate
    118 MW
    IT power
    Not reported.Epoch AI dates the first capacity to November 2026. Epoch AI's latest entry, November 1, 2026: "Building 1 expected to be fully operational, assuming a 3-month fit-out period." Epoch AI projects 470 MW of IT power by December 2027.
    São Paulo, Brazil
    Multi-tenantPlanned14 MW
    basis not stated
    not stated
    basis not stated
    Grid (largely hydro).Planned.
    Claude, Texas, United States
    GoogleUnder construction1.0 GW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Energy companies Epoch AI names: Serena. Fuel and contract terms are not reported there.Epoch AI projects the first capacity in March 2027. Epoch AI's latest entry, April 16, 2026: "Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures." Epoch AI projects 1,006 MW of IT power by October 2027.
    Visakhapatnam, Andhra Pradesh, India
    GoogleUnder construction1 GW
    basis not stated
    not stated
    basis not stated
    Adani's renewable portfolio is the stated supply; an international subsea cable landing is part of the plan.Groundbreaking 28 April 2026; the $15 billion runs 2026–2030.
    Sterling, Virginia, United States
    GoogleOperating77 MW
    IT power · Epoch AI estimate
    77 MW
    IT power
    Not reported.Epoch AI dates the first capacity to June 2026. Epoch AI's latest entry, June 16, 2026: "Building 1 is operational, based off of colored motion artifacts from cooling towers and direct visual verification."
    Bristow, Virginia, United States
    Google DeepMindOperating238 MW
    IT power · Epoch AI estimate
    238 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2024. Epoch AI's latest entry, May 20, 2026: "Building 3 is operational, based off of colored motion artifacts from cooling towers."
    Cedar Rapids, Iowa, United States
    GoogleUnder construction261 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, April 16, 2026: "Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction." Epoch AI projects 261 MW of IT power by May 2027.
    Columbus, Ohio, United States
    GoogleOperating386 MW
    IT power · Epoch AI estimate
    303 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2024. Epoch AI's latest entry, August 5, 2026: "Confirmation that Building 4 is complete." Epoch AI projects 386 MW of IT power by July 2027.
    Council Bluffs, Iowa, United States
    GoogleOperating237 MW
    IT power · Epoch AI estimate
    237 MW
    IT power
    Not reported.Epoch AI dates the first capacity to November 2024. Epoch AI's latest entry, July 7, 2026: "Building 3 is operational."
    Fort Wayne, Indiana, United States
    GoogleUnder construction863 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, August 19, 2026: "Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning." Epoch AI projects 863 MW of IT power by June 2028.
    Kansas City, Missouri, United States
    GoogleOperating105 MW
    IT power · Epoch AI estimate
    105 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2026. Epoch AI's latest entry, August 1, 2026: "Building 1 operational."
    Lancaster, Ohio, United States
    GoogleOperating137 MW
    IT power · Epoch AI estimate
    137 MW
    IT power
    Not reported.Epoch AI dates the first capacity to January 2024. Epoch AI's latest entry, March 12, 2026: "At this point, Building 1 and 2 have since already been operational."
    Lincoln, Nebraska, United States
    GoogleOperating283 MW
    IT power · Epoch AI estimate
    141 MW
    IT power
    Not reported.Epoch AI dates the first capacity to May 2026. Epoch AI's latest entry, May 12, 2026: "Building 1 operational." Epoch AI projects 283 MW of IT power by October 2027.
    Mesa, Arizona, United States
    GoogleOperating183 MW
    IT power · Epoch AI estimate
    183 MW
    IT power
    Not reported.Epoch AI dates the first capacity to July 2025. Epoch AI's latest entry, August 15, 2026: "Building 2 is operational."
    Midlothian, Texas, United States
    GoogleOperating103 MW
    IT power · Epoch AI estimate
    103 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2026. Epoch AI's latest entry, July 1, 2026: "Estimated full completion of the expanded row of cooling towers and backup generators for Building 1."
    New Albany, Ohio, United States
    GoogleOperating333 MW
    IT power · Epoch AI estimate
    333 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2024. Epoch AI's latest entry, May 18, 2026: "Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building."
    Omaha, Nebraska, United States
    GoogleOperating395 MW
    IT power · Epoch AI estimate
    237 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2024. Epoch AI's latest entry, June 30, 2026: "Building 3 is operational (estimate)." Epoch AI projects 395 MW of IT power by July 2028.
    Papillion, Nebraska, United States
    GoogleOperating237 MW
    IT power · Epoch AI estimate
    237 MW
    IT power
    Not reported.Epoch AI dates the first capacity to January 2023. Epoch AI's latest entry, May 4, 2026: "Building 4 shell mostly complete, Building 5 steel framing is underway."
    Pryor, Oklahoma, United States
    GoogleOperating368 MW
    IT power · Epoch AI estimate
    368 MW
    IT power
    Not reported.Epoch AI dates the first capacity to July 2024. Epoch AI's latest entry, September 6, 2026: "Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th."
    Red Oak, Texas, United States
    GoogleOperating154 MW
    IT power · Epoch AI estimate
    77 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2025. Epoch AI's latest entry, February 6, 2026: "Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot." Epoch AI projects 154 MW of IT power by December 2026.
    Storey County, Nevada, United States
    GoogleOperating300 MW
    IT power · Epoch AI estimate
    161 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2023. Epoch AI's latest entry, April 13, 2026: "Building 3 has a partially complete shell, electrical and mechanical equipment." Epoch AI projects 300 MW of IT power by June 2027.
    The Dalles, Oregon, United States
    GoogleOperating154 MW
    IT power · Epoch AI estimate
    154 MW
    IT power
    Not reported.Epoch AI dates the first capacity to March 2025. Epoch AI's latest entry, April 29, 2026: "Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building."
    Waltham Cross, England, United Kingdom
    GoogleOperating88 MW
    IT power · Epoch AI estimate
    88 MW
    IT power
    Energy companies Epoch AI names: Shell Energy Europe and Engie. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to September 2025. Epoch AI's latest entry, April 23, 2026: "Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image; no capacity change since September 2025."
    Wilbarger County, Texas, United States
    GoogleUnder constructionnot stated
    basis not stated
    not stated
    basis not stated
    AES named as the power partner.Under construction.
    Homer City, Pennsylvania, United States
    Not yet namedUnder construction4.5 GW
    basis not stated
    not stated
    basis not stated
    Seven gas generating units on the site of the former coal plant, 4.4–4.5 GW, supplied by EQT.Construction began 2025.
    Horinger, Inner Mongolia, China
    HuaweiOperating351 MW
    IT power · Epoch AI estimate
    170 MW
    IT power
    Not reported.Epoch AI dates the first capacity to June 2025. Epoch AI's latest entry, August 18, 2026: "In the South Zone, Building 5 is operational, based on its structural completion, and the colored motion artifacts on the some of the cooling tower fans." Epoch AI projects 351 MW of IT power by February 2028.
    Wuhu, Anhui, China
    HuaweiOperating453 MW
    IT power · Epoch AI estimate
    197 MW
    IT power
    Not reported.Epoch AI dates the first capacity to January 2025. Epoch AI's latest entry, November 1, 2026: "Five buildings are operational." Epoch AI projects 453 MW of IT power by December 2027.
    Riyadh and Dammam, Saudi Arabia
    Humain (PIF)Under construction200 MW
    basis not stated
    not stated
    basis not stated
    Not stated.Under construction.
    Trenton, South Carolina, United States
    MetaOperating129 MW
    IT power · Epoch AI estimate
    129 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2026. Epoch AI's latest entry, November 5, 2026: "Building 2 is operational assuming a 3 month lag compared to Building 1."
    Bowling Green, Ohio, United States
    MetaUnder construction422 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Energy companies Epoch AI names: Williams. Fuel and contract terms are not reported there.Epoch AI projects the first capacity in February 2027. Epoch AI's latest entry, July 30, 2026: "Roofs of Buildings 1 and 2 are more than halfway complete." Epoch AI projects 422 MW of IT power by January 2028.
    Cheyenne, Wyoming, United States
    MetaOperating207 MW
    IT power · Epoch AI estimate
    152 MW
    IT power
    Not reported.Epoch AI dates the first capacity to July 2026. Epoch AI's latest entry, July 25, 2026: "Both buildings estimated to be operational." Epoch AI projects 207 MW of IT power by February 2027.
    Eagle Mountain, Utah, United States
    MetaOperating133 MW
    IT power · Epoch AI estimate
    133 MW
    IT power
    Energy companies Epoch AI names: Williams. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to December 2025. Epoch AI's latest entry, May 2, 2026: "Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances."
    El Paso, Texas, United States
    MetaUnder construction1 GW
    basis not stated
    not stated
    basis not stated
    Not stated in Meta's announcement.Meta confirmed on March 26, 2026 that the campus will grow to 1 gigawatt. CNBC reported the capacity is due by 2028.
    Gallatin, Tennessee, United States
    MetaOperating87 MW
    IT power · Epoch AI estimate
    87 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2026. Epoch AI's latest entry, August 24, 2026: "Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion."
    Toney, Alabama, United States
    MetaOperating146 MW
    IT power · Epoch AI estimate
    146 MW
    IT power
    Energy companies Epoch AI names: Tennessee Valley Authority, NextEra Energy Resources and First Solar. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to March 2026. Epoch AI's latest entry, June 2, 2026: "We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines."
    Richland Parish, Louisiana, United States
    MetaUnder construction5 GW
    basis not stated
    not stated
    basis not stated
    Three new Entergy gas plants; Phase I power approved by the Louisiana PSC, the Phase II expansion package under review.First phase expected online 2028; full build-out reported to run to 2030.
    Jeffersonville, Indiana, United States
    MetaOperating178 MW
    IT power · Epoch AI estimate
    178 MW
    IT power
    Not reported.Epoch AI dates the first capacity to June 2026. Epoch AI's latest entry, June 4, 2026: "Building 1 and 2 are operational."
    Kuna, Idaho, United States
    MetaOperating152 MW
    IT power · Epoch AI estimate
    152 MW
    IT power
    Energy companies Epoch AI names: Idaho Power Company. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to June 2026. Epoch AI's latest entry, June 1, 2026: "Building 1 and 2 are operational."
    Lebanon, Indiana, United States
    MetaUnder construction1 GW
    basis not stated
    not stated
    basis not stated
    Not stated.Groundbreaking February 2026; opening expected at the end of 2027 or in early 2028.
    Los Lunas, New Mexico, United States
    MetaOperating218 MW
    IT power · Epoch AI estimate
    118 MW
    IT power
    Not reported.Epoch AI dates the first capacity to March 2026. Epoch AI's latest entry, October 26, 2026: "Building 2 (a tent like building) is operational." Epoch AI projects 218 MW of IT power by January 2028.
    Montgomery, Alabama, United States
    MetaOperating358 MW
    IT power · Epoch AI estimate
    153 MW
    IT power
    Not reported.Epoch AI dates the first capacity to June 2026. Epoch AI's latest entry, June 18, 2026: "We estimate Buildings 1 and 2 are operational." Epoch AI projects 358 MW of IT power by February 2027.
    New Albany, Ohio, United States
    MetaUnder construction1 GW
    basis not stated
    not stated
    basis not stated
    Behind-the-meter natural gas built with Williams; Meta's January 2026 Vistra and Oklo nuclear agreements are framed around this cluster.Meta said it comes online in 2026; a "tents over buildings" design chosen for speed.
    Rosemount, Minnesota, United States
    MetaOperating178 MW
    IT power · Epoch AI estimate
    178 MW
    IT power
    Not reported.Epoch AI dates the first capacity to June 2026. Epoch AI's latest entry, June 19, 2026: "Buildings 1 and 2 are estimated to be operational."
    Springfield, Nebraska, United States
    MetaOperating80 MW
    IT power · Epoch AI estimate
    80 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2026. Epoch AI's latest entry, August 2, 2026: "Building 1 is operational (estimate)."
    Temple, Texas, United States
    MetaOperating178 MW
    IT power · Epoch AI estimate
    178 MW
    IT power
    Not reported.Epoch AI dates the first capacity to December 2025. Epoch AI's latest entry, September 30, 2026: "Building 3 is operational."
    Hillsboro, Oregon, United States
    MetaOperating180 MW
    IT power · Epoch AI estimate
    180 MW
    IT power
    Energy companies Epoch AI names: Portland General Electric and Avangrid. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to August 2023. Epoch AI's latest entry, April 17, 2026: "All four buildings are operational."
    Atlanta, Georgia, United States
    Microsoft (OpenAI workloads)Operatingnot stated
    basis not stated
    not stated
    basis not stated
    Grid; designed with no UPS or generator sets, ~140 kW per rack.Online November 2025.
    Mount Pleasant, Wisconsin, United States
    Microsoft (OpenAI workloads)Operating2 GW
    basis not stated
    not stated
    basis not stated
    Grid (We Energies); closed-loop liquid cooling.First facility reported fully operational June 2026; the adjacent second facility reported for 2028; Nadella: "scale to two gigawatts".
    Goodyear, Arizona, United States
    OpenAI · MicrosoftOperating202 MW
    IT power · Epoch AI estimate
    202 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2023. Epoch AI's latest entry, April 27, 2026: "Foundations appear to be underway for Building 5 and 6, just north of Building 4."
    Hyderabad, India
    MicrosoftOperating600 MW
    basis not stated
    not stated
    basis not stated
    Not stated.Generally available August 6, 2026, as Microsoft's fourth cloud region in India.
    Cumming, Iowa, United States
    MicrosoftOperating190 MW
    IT power · Epoch AI estimate
    190 MW
    IT power
    Not reported.Epoch AI dates the first capacity to January 2021. Epoch AI's latest entry, June 16, 2026: "No notable changes since October."
    San Antonio, Texas, United States
    MicrosoftOperating47 MW
    IT power · Epoch AI estimate
    47 MW
    IT power
    Not reported.Epoch AI dates the first capacity to July 2024. Epoch AI's latest entry, March 31, 2026: "Building 2 fully operational, Building 1 expanded."
    San Antonio, Texas, United States
    MicrosoftOperating75 MW
    IT power · Epoch AI estimate
    75 MW
    IT power
    Not reported.Epoch AI dates the first capacity to May 2024. Epoch AI's latest entry, February 4, 2026: "Site has already been completed, with no more visible construction on any building."
    Vineland, New Jersey, United States
    MicrosoftOperating50 MW
    IT power · Epoch AI estimate
    50 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2026. Epoch AI's latest entry, July 12, 2026: "Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating."
    Kvandal, Narvik, Norway
    Microsoft (replacing OpenAI)Under construction230 MW
    basis not stated
    not stated
    basis not stated
    100% renewable (hydro) above the Arctic Circle.First 230 MW phase targeted for H2 2026 (aggregator figure); Microsoft's 30,000 NVIDIA Rubin GPUs delivered in 2027; a 520 MW longer-term plan.
    Mäntsälä, Uusimaa, Finland
    NebiusOperating145 MW
    IT power · Epoch AI estimate
    75 MW
    IT power
    Not reported.Epoch AI dates the first capacity to October 2024. Epoch AI's latest entry, June 29, 2026: "All three buildings in the first phase are operational." Epoch AI projects 145 MW of IT power by December 2027.
    Reykjanesbær, Southern Peninsula, Iceland
    NscaleOperating10 MW
    IT power · Epoch AI estimate
    5 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2026. Epoch AI's latest entry, July 27, 2026: "Building 1 is operational (estimate)." Epoch AI projects 10 MW of IT power by December 2026.
    Loughton, England, United Kingdom
    MicrosoftPlanned90 MW
    basis not stated
    not stated
    basis not stated
    Grid connection through UK Power Networks; its date is contested (see Contested).Announced in September 2025 at 50 MW, scalable to 90 MW, with 23,040 NVIDIA GB300 GPUs due from the first quarter of 2027.
    Tuas, Singapore, Singapore
    Multi-tenantOperating58 MW
    basis not stated
    not stated
    basis not stated
    Not stated in the report read.Opened in February 2026.
    Batam, Riau Islands, Indonesia
    OracleOperating72 MW
    IT power · Epoch AI estimate
    72 MW
    IT power
    Not reported.Epoch AI dates the first capacity to May 2025. Epoch AI's latest entry, May 6, 2026: "The three buildings look unchanged since March."
    Laramie County, Wyoming, United States
    Not namedStalled or cut back1.8 GW
    basis not stated
    not stated
    basis not stated
    Tallgrass is building the Cheyenne Power Hub, a natural gas plant dedicated to the campus in the Switchgrass Industrial Park.Announced in July 2025. Crusoe disclosed on June 9, 2026 that it had paused development; the Wyoming Tribune Eagle reported the same day that it had left the site about two months earlier. Tallgrass said its own work continues.
    Carson County, Texas, United States
    TensorWave (first lease)Under constructionnot stated
    basis not stated
    not stated
    basis not stated
    Private on-site generation. Fermi says about 6 gigawatts of a planned 17 gigawatts is permitted, with first power targeted for 2026.Fermi signed its first binding lease on August 10, 2026: a facility with 222 MW of total facility power for TensorWave, delivered in phases from the second half of 2027.
    Amsterdam, North Holland, Netherlands
    Not namedUnder construction78 MW
    basis not stated
    0 MW
    basis not stated
    A private substation with a firm connection to the 50 kV grid; Pure DC says it is built and live.Data hall development began in January 2026, per Pure DC. The page gives no completion date.
    Fairfax, Iowa, United States
    MetaUnder construction1.1 GW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Energy companies Epoch AI names: Alliant Energy. Fuel and contract terms are not reported there.Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, October 23, 2026: "Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared." Epoch AI projects 1,133 MW of IT power by November 2027.
    Eagle Mountain, Utah, United States
    MetaUnder construction304 MW
    IT power · Epoch AI estimate
    0 MW
    IT power
    Not reported.Epoch AI projects the first capacity in December 2026. Epoch AI's latest entry, May 2, 2026: "Building 1 roof finished." Epoch AI projects 304 MW of IT power by July 2027.
    Sandston, Virginia, United States
    Not reportedOperating238 MW
    IT power · Epoch AI estimate
    238 MW
    IT power
    Energy companies Epoch AI names: Dominion Energy. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to January 2024. Epoch AI's latest entry, February 13, 2026: "No changes to the site since December 2025."
    Sandston, Virginia, United States
    Not reportedOperating180 MW
    IT power · Epoch AI estimate
    180 MW
    IT power
    Energy companies Epoch AI names: Dominion Energy. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to February 2025. Epoch AI's latest entry, May 14, 2026: "Building 5 is estimated to be operational, based on the previous entry."
    Sandston, Virginia, United States
    Not reportedOperating240 MW
    IT power · Epoch AI estimate
    144 MW
    IT power
    Energy companies Epoch AI names: Dominion Energy. Fuel and contract terms are not reported there.Epoch AI dates the first capacity to February 2026. Epoch AI's latest entry, May 14, 2026: "Building 2 and 3 are operational, based on the previous entry." Epoch AI projects 240 MW of IT power by February 2027.
    Jamnagar, Gujarat, India
    Meta (lessee)Planned168 MW
    basis not stated
    not stated
    basis not stated
    Reliance's Jamnagar renewable and gas complex.Delivery within two years of June 2026.
    Ulsan, South Korea
    Amazon Web ServicesUnder construction100 MW
    basis not stated
    0 MW
    basis not stated
    Not stated in the reports read.Ground was broken on August 29, 2025. On November 21, 2026 the facility was reported 71% complete, with operations due in late 2027.
    Tomakomai, Hokkaido, Japan
    SoftBank Corp.Under construction300 MW
    basis not stated
    not stated
    basis not stated
    Hokkaido renewables are the stated pitch.Under construction; SoftBank said in February 2026 that operations start in fiscal 2026, which ends March 31, 2027. The first phase is about 50 MW.
    Melbourne, Victoria, Australia
    FirmusOperating41 MW
    IT power · Epoch AI estimate
    41 MW
    IT power
    Not reported.Epoch AI dates the first capacity to August 2026. Epoch AI's latest entry, August 9, 2026: "Building 1 is operational (estimate)."
    Manassas, Virginia, United States
    Not reportedOperating348 MW
    IT power · Epoch AI estimate
    85 MW
    IT power
    Not reported.Epoch AI dates the first capacity to October 2024. Epoch AI's latest entry, February 14, 2026: "All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery." Epoch AI projects 348 MW of IT power by January 2028.
    Abilene, Texas, United States
    OpenAI (Oracle-operated)Operating1.2 GW
    facility power
    618 MW
    basis not stated
    Grid plus on-site gas turbines; the campus sits beside a wind farm. Figures are total facility power.First phase live September 2025. Oracle said on September 10, 2026 that six of eight buildings, 618 MW, had been delivered to the customer. It gave no date for the last two; the campus was first due complete by mid-2026. Epoch AI's satellite review estimates that buildings 7 and 8 were running by November 1, 2026; no company has confirmed it.
    Doña Ana County, New Mexico, United States
    OpenAI (Oracle-operated)Under construction2.2 GW
    facility power
    0 MW
    facility power
    Grid; facility-power figure.Construction had advanced well past foundations by June 22, 2026, with no building yet running. Epoch AI projects completion by the end of 2028.
    Lordstown, Ohio, United States
    OpenAI (SoftBank-owned hardware)Under constructionnot stated
    facility power
    0 MW
    facility power
    The former GM plant already has a substation connected.Active construction with the roof mostly on by July 30, 2026, though no building was running. Epoch AI projects operation from March 2027.
    Milam County, Texas, United States
    OpenAI (SoftBank-owned hardware)Under construction1.2 GW
    facility power
    0 MW
    facility power
    SB Energy's own generation and grid; a "fast-build" design.Steel framing and roofing were under way on building 1 by March 23, 2026. No delivery had been reported as of November 12, 2026. Epoch AI projects the site fully running by the end of 2028.
    Port Washington, Wisconsin, United States
    OpenAI (Oracle-operated)Under construction1.3 GW
    facility power
    0 MW
    facility power
    Grid (We Energies); facility-power figure.By July 24, 2026, buildings 1 and 2 were about half roofed and the building 3 foundation was half done. Epoch AI projects all four buildings running by the end of 2028.
    Saline Township, Michigan, United States
    OpenAI (Oracle-operated)Under construction1.4 GW
    facility power
    0 MW
    facility power
    DTE Energy supplies the grid connection.Groundwork for building 1 was visible by March 12, 2026. DTE Energy's maximum load is scheduled for December 2027 and can move out a year; Epoch AI projects the three buildings running by the end of 2028.
    Shackelford County, Texas, United States
    OpenAI (Oracle-operated)Under construction2 GW
    facility power
    0 MW
    facility power
    Grid (ERCOT); facility-power figure.By September 4, 2026, buildings 1 to 5 had their shells complete and roofs on, with cooling and backup generators going in at buildings 1 to 3. Vantage targets the first building in the second half of 2026; Epoch AI projects building 1 running in August 2027 and all ten by November 2028.
    Abu Dhabi, United Arab Emirates
    OpenAI · G42Under construction5 GW
    basis not stated
    not stated
    basis not stated
    Not stated for the campus; the UAE grid is gas and nuclear (Barakah) backed.First 200 MW of a 1 GW cluster due in 2026; the rest of the 1 GW and the 5 GW campus have no confirmed dates.
    Sines, Setúbal, Portugal
    MicrosoftOperating233 MW
    IT power · Epoch AI estimate
    33 MW
    IT power
    Not reported.Epoch AI dates the first capacity to April 2026. Epoch AI's latest entry, August 16, 2026: "Satellite imagery shows two black outlines, suggesting two buildings going up on a second adjacent site." Epoch AI projects 233 MW of IT power by September 2027.
    Goodyear, Arizona, United States
    Not reportedOperating220 MW
    IT power · Epoch AI estimate
    64 MW
    IT power
    Not reported.Epoch AI dates the first capacity to May 2026. Epoch AI's latest entry, May 1, 2026: "Estimated: AI building 1 should be operational." Epoch AI projects 220 MW of IT power by January 2030.
    Montréal and Québec City, Canada
    Multi-tenantOperating178 MW
    basis not stated
    178 MW
    basis not stated
    Hydro-Québec.Operational.
    San Antonio, Texas, United States
    Not reportedOperating128 MW
    IT power · Epoch AI estimate
    32 MW
    IT power
    Not reported.Epoch AI dates the first capacity to February 2026. Epoch AI's latest entry, February 15, 2026: "Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well." Epoch AI projects 128 MW of IT power by August 2027.
    Ulanqab, Inner Mongolia, China
    ByteDanceOperating700 MW
    IT power · Epoch AI estimate
    221 MW
    IT power
    Not reported.Epoch AI dates the first capacity to July 2025. Epoch AI's latest entry, May 6, 2026: "Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining." Epoch AI projects 700 MW of IT power by September 2027.
    Memphis, Tennessee / Southaven, Mississippi, United States
    xAI (SpaceX)Operating2 GW
    IT power
    1 GW
    basis not stated
    Largely off-grid: on-site gas turbines and batteries; TVA had not committed firm grid capacity as of the sources read.Crossed ~1 GW in 2026; 440,000 GB300 GPUs reported in use by late September 2026 with a further 660,000 expected by year-end.
    Atlanta, Georgia, United States
    SpaceXAIOperating17 MW
    IT power · Epoch AI estimate
    17 MW
    IT power
    Not reported.Epoch AI dates the first capacity to February 2025. Epoch AI's latest entry, July 10, 2026: "No significant change to the building since the August 2025 image."
    Kulai, Johor, Malaysia
    Not reportedOperating284 MW
    IT power · Epoch AI estimate
    113 MW
    IT power
    Not reported.Epoch AI dates the first capacity to November 2025. Epoch AI's latest entry, July 13, 2026: "Satellite imagery confirms Buildings 1 and 2 are structurally complete." Epoch AI projects 284 MW of IT power by August 2028.

    Records marked Epoch AI estimate come from Epoch AI, "AI data centers" (epoch.ai/data/ai-data-centers), used under the Creative Commons Attribution license. They are read from satellite imagery, permits and public documents, on an IT power basis, and are not operator statements.

    Energy assets and grid rules

    AssetKindServesCapacityTiming
    Londonderry Township, Pennsylvania, United States
    Nuclear restartMicrosoft — 20-year power purchase agreement835 MWConstellation targets 2027, "ahead of schedule"; the NRC issued its environmental finding of no significant impact in late September 2026, with exemption and license-amendment decisions still pending.
    Covert, Michigan, United States
    Nuclear restartMichigan grid (Wolverine Power / Hoosier Energy offtake); the first US restart of a closed reactor800 MWFuel loading began at the end of August 2026 and paused when a used fuel assembly tilted in the reactor vessel. On October 13, 2026 the NRC approved a one-time license amendment to move that assembly to the spent fuel pool. Holtec still says 2026; no restart date has been set.
    Salem Township, Pennsylvania, United States
    Existing nuclear (PPA)Amazon Web Services — the adjacent campus and other Pennsylvania sites1.9 GW840–1,200 MW in 2029, 1,680–1,920 MW by 2032 at the latest.
    Oak Harbor and Perry, Ohio; Shippingport, Pennsylvania, United States
    Existing nuclear (PPA)Meta — Prometheus and the PJM campuses2.6 GWPurchases begin late 2026; uprate capacity added through 2034.
    Pike County, Ohio, United States
    New nuclear / SMRMeta1.2 GWThe full 1.2 GW is targeted by 2034; no unit dates stated.
    Sites for Meta-funded units not disclosed, United States
    New nuclear / SMRMeta — up to eight Natrium units, rights to output690 MWThe six further units are targeted for delivery by 2035.
    Oak Ridge, Tennessee, United States
    New nuclear / SMRGoogle — clean-energy attributes for its Tennessee and Alabama data centers50 MWOperations scheduled to begin 2030.
    Richland, Washington, United States
    New nuclear / SMRAmazon-funded; Pacific Northwest data centers320 MWTargeting construction by 2030.
    Richland Parish, Louisiana, United States
    Gas (on-site or new plant)Meta Hyperionnot statedFirst Hyperion phase 2028. On April 15, 2026 the PSC voted 4 to 1 to fast-track the seven-plant request. The final vote, earlier reported for November 18, is now expected at the PSC's December 10, 2026 meeting.
    New Albany, Ohio, United States
    Gas (on-site or new plant)Meta Prometheus400 MWWilliams targets Socrates South in the third quarter of 2026 and Socrates North in the fourth.
    Southaven, Mississippi, United States
    Gas (on-site or new plant)xAI Colossus 2not statedA 150 MW grid build-out not scheduled to energize until late 2026.
    Homer City, Pennsylvania, United States
    Gas (on-site or new plant)The Homer City energy campus (tenant not yet named)4.5 GWConstruction from 2025.
    Southeastern United States (2,500 acres; state not stated), United States
    Gas (on-site or new plant)Seeking an AI tenant1.2 GWPlanned.
    Narvik, Norway
    RenewableThe Narvik AI gigafactory230 MWWith the campus.
    Dublin, Ireland
    Grid connection policyEvery new Dublin-area data centernot statedIn force from 2026 applications.
    Amsterdam, Netherlands
    Grid connection policyHyperscale projects in the Amsterdam regionnot statedIn force.
    Singapore, Singapore
    Grid connection policyNew data centers in Singaporenot statedRolling.
    Browse 1,974 mapped data centers from OpenStreetMap in this view
    Evidence review queue and change history

    Public editorial quality queue for this curated register. Review flags identify missing evidence, not proof a project is late or incorrect. Source revisions are reviewed in GitHub before publication.

    • Stargate Abilene: Source review overdue; Historical evidence requires current status check
    • Stargate Shackelford County: Source review overdue; Historical evidence requires current status check
    • Stargate Doña Ana (Project Jupiter): Source review overdue; Historical evidence requires current status check
    • Stargate Milam County: Source review overdue; Historical evidence requires current status check
    • Stargate Port Washington (Lighthouse): Source review overdue; Historical evidence requires current status check
    • Stargate Saline Township (The Barn): Source review overdue; Historical evidence requires current status check
    • Stargate Lordstown: Source review overdue; Historical evidence requires current status check; Epoch reports less than 300 MW, not an exact 300 MW. The exact capacity is withheld pending clarification; the source describes manufacturing activity and limited campus construction.
    • Meta Hyperion: Metric-level verification not recorded; Full-build power basis not stated
    • Meta Prometheus: Metric-level verification not recorded; Full-build power basis not stated
    • Meta Lebanon: Metric-level verification not recorded; Full-build power basis not stated
    • xAI Colossus 2: Metric-level verification not recorded; Operating power basis not confirmed
    • Amazon Project Rainier: Metric-level verification not recorded; Full-build power basis not stated
    • Microsoft Fairwater Wisconsin: Metric-level verification not recorded; Full-build power basis not stated
    • Microsoft Fairwater Atlanta: Metric-level verification not recorded; Full-build power basis not stated
    • Google Wilbarger County: Metric-level verification not recorded; Full-build power basis not stated
    • Homer City Energy Campus: Metric-level verification not recorded; Full-build power basis not stated
    • Stargate UAE (UAE–US AI Campus): Metric-level verification not recorded; Full-build power basis not stated
    • Humain AI Data Centers: Metric-level verification not recorded; Full-build power basis not stated
    • Narvik AI gigafactory (ex-Stargate Norway): Metric-level verification not recorded; Full-build power basis not stated
    • Campus AI (MGX · Mistral) Île-de-France: Metric-level verification not recorded; Full-build power basis not stated
    • Google AI Hub Visakhapatnam: Metric-level verification not recorded; Full-build power basis not stated
    • Reliance–Meta Jamnagar: Metric-level verification not recorded; Full-build power basis not stated
    • Microsoft India South Central region: Metric-level verification not recorded; Full-build power basis not stated; The legacy mid-2026 go-live target has elapsed while the record remains under construction. Obtain a dated commissioning update; do not infer completion.
    • SoftBank Tomakomai AI data center: Metric-level verification not recorded; Full-build power basis not stated
    • Data Center Valley, Ekibastuz: Metric-level verification not recorded; Full-build power basis not stated
    • Vantage Québec expansion: Metric-level verification not recorded; Full-build power basis not stated; Operating power basis not confirmed
    • Equinix SP7 São Paulo: Metric-level verification not recorded; Full-build power basis not stated
    • AWS Peru region: Metric-level verification not recorded; Full-build power basis not stated
    • Meta El Paso: Metric-level verification not recorded; Full-build power basis not stated
    • Project Matador: Metric-level verification not recorded; Full-build power basis not stated
    • Project Jade: Metric-level verification not recorded; Full-build power basis not stated
    • Nscale Loughton AI Campus: Metric-level verification not recorded; Full-build power basis not stated
    • SK-AWS Ulsan AI data center: Metric-level verification not recorded; Full-build power basis not stated
    • AirTrunk TOK1: Metric-level verification not recorded; Full-build power basis not stated
    • Nxera DC Tuas: Metric-level verification not recorded; Full-build power basis not stated
    • CyrusOne FRA7: Metric-level verification not recorded
    • CDC Marsden Park: Metric-level verification not recorded
    • Pure DC AMS01: Metric-level verification not recorded; Full-build power basis not stated
    • Echelon DUB10: Metric-level verification not recorded
    • Southgate Melbourne: Metric-level verification not recorded
    • Alibaba Zhangbei: Metric-level verification not recorded
    • Envision Galaxy Ulanqab: Metric-level verification not recorded
    • Huawei Horinger: Metric-level verification not recorded
    • Huawei Wuhu: Metric-level verification not recorded
    • VNET Bayin Ulanqab: Metric-level verification not recorded
    • Nebius Mantsala: Metric-level verification not recorded
    • Nscale Keflavik: Metric-level verification not recorded
    • Oracle Batam: Metric-level verification not recorded
    • Bridge Data Centres MY06: Metric-level verification not recorded
    • DayOne Kempas: Metric-level verification not recorded
    • DayOne Nusajaya: Metric-level verification not recorded
    • YTL Johor: Metric-level verification not recorded
    • CoreWeave Norway: Metric-level verification not recorded
    • Start Campus Sines Data Campus: Metric-level verification not recorded
    • EcoDataCenter 2: Metric-level verification not recorded
    • Google Waltham Cross: Metric-level verification not recorded
    • Amazon Madison Mega Site: Metric-level verification not recorded
    • Amazon Ridgeland: Metric-level verification not recorded
    • Anthropic Barber Lake: Metric-level verification not recorded
    • Anthropic Lake Mariner: Metric-level verification not recorded
    • AWS Berwick: Metric-level verification not recorded
    • AWS New Albany: Metric-level verification not recorded
    • Colossus 1: Metric-level verification not recorded
    • Core42 Lake Mariner: Metric-level verification not recorded
    • CoreWeave Chester VA: Metric-level verification not recorded
    • CoreWeave Dalton 1 & 2: Metric-level verification not recorded
    • CoreWeave Denton TX: Metric-level verification not recorded
    • CoreWeave Ellendale ND: Metric-level verification not recorded
    • Coreweave Helios: Metric-level verification not recorded
    • CoreWeave Lancaster Greenfield site: Metric-level verification not recorded
    • CoreWeave Marble NC: Metric-level verification not recorded
    • CoreWeave Muskogee OK: Metric-level verification not recorded
    • Crusoe Abilene Expansion: Metric-level verification not recorded
    • Goodnight: Metric-level verification not recorded
    • Google Arcola: Metric-level verification not recorded
    • Google Bristow: Metric-level verification not recorded
    • Google Cedar Rapids: Metric-level verification not recorded
    • Google Columbus: Metric-level verification not recorded
    • Google Council Bluffs (East): Metric-level verification not recorded
    • Google Fort Wayne: Metric-level verification not recorded
    • Google Kansas City East: Metric-level verification not recorded
    • Google Lancaster: Metric-level verification not recorded
    • Google Lincoln: Metric-level verification not recorded
    • Google Mesa: Metric-level verification not recorded
    • Google Midlothian: Metric-level verification not recorded
    • Google New Albany: Metric-level verification not recorded
    • Google Omaha: Metric-level verification not recorded
    • Google Papillion: Metric-level verification not recorded
    • Google Pryor (North): Metric-level verification not recorded
    • Google Red Oak: Metric-level verification not recorded
    • Google Storey County: Metric-level verification not recorded
    • Google The Dalles: Metric-level verification not recorded
    • Meta Aiken: Metric-level verification not recorded
    • Meta Bowling Green: Metric-level verification not recorded
    • Meta Cheyenne: Metric-level verification not recorded
    • Meta Eagle Mountain: Metric-level verification not recorded
    • Meta Gallatin: Metric-level verification not recorded
    • Meta Huntsville: Metric-level verification not recorded
    • Meta Jeffersonville: Metric-level verification not recorded
    • Meta Kuna: Metric-level verification not recorded
    • Meta Los Lunas: Metric-level verification not recorded
    • Meta Montgomery: Metric-level verification not recorded
    • Meta Rosemount: Metric-level verification not recorded
    • Meta Sarpy: Metric-level verification not recorded
    • Meta Temple: Metric-level verification not recorded
    • Meta-QTS Hillsboro 2: Metric-level verification not recorded
    • Microsoft Goodyear: Metric-level verification not recorded
    • Microsoft Project Osmium: Metric-level verification not recorded
    • Microsoft SAT14: Metric-level verification not recorded
    • Microsoft SAT40: Metric-level verification not recorded
    • Microsoft-Nebius New Jersey: Metric-level verification not recorded
    • QTS Cedar Rapids: Metric-level verification not recorded
    • QTS Eagle Mountain: Metric-level verification not recorded
    • QTS Richmond 1: Metric-level verification not recorded
    • QTS Richmond 2: Metric-level verification not recorded
    • QTS Richmond 3: Metric-level verification not recorded
    • STACK Infrastructure NVA02: Metric-level verification not recorded
    • Stream Phoenix: Metric-level verification not recorded
    • Vantage TX1: Metric-level verification not recorded
    • xAI QTS Atlanta: Metric-level verification not recorded

    Reviewed editorial changes

    • 2026-10-18 · capacity evidence

      Before: Generic source date and reported capacity

      After: Explicit third-party estimate, publication/effective/review dates and metric bindings

      Epoch explains its facility-power estimates and April revision.

      Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18
    • 2026-10-18 · capacityMw

      Before: 300 MW exact

      After: Exact value unknown; source upper bound <300 MW retained in notes

      Do not convert a bound to an exact measurement.

      Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18
    • 2026-10-18 · editorial interpretation

      Before: Described as running on new gas

      After: Under construction with gas-backed supply planned

      Align interpretation with the record's project phase.

    Demand and constraints

    How much power, and what is in the way

    • Global data center electricity, 2025

      485 TWh

      About 1.5% of world electricity, before most of the campuses on this map draw power.

      IEA: Key Questions on Energy and AI (2026), executive summaryPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: 2026-12-12 · Legacy source/access date: 2026-10-23

    • Global data center electricity, 2030 (IEA)

      ~950 TWh, ~3% of demand

      The IEA projects roughly twice the 2025 consumption by 2030; AI-focused data center electricity use triples over 2025-2030 in this outlook.

      IEA: Key Questions on Energy and AI (2026), executive summaryPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: 2026-12-12 · Legacy source/access date: 2026-10-23

    • US increase to 2030 (IEA)

      up to +240 TWh, +130% on 2024

      The US and China account for most of the growth; the US is where the grid fight is.

      DCD - IEA: data center energy consumption set to double by 2030Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-04-10

    • IT capacity under construction, end-Sept 2025 (BloombergNEF)

      23.1 GW across 831 sites; 15.9 GW in the US

      A reported construction pipeline with its own coverage and IT-power basis; not directly comparable with this selected campus register.

      Data Center Knowledge - AI-first hyperscalers: 2026's sprint meets the power bottleneckPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-15

    • Of 140 projects and 16 GW slated for 2026 completion (Sightline Climate)

      30–50% slips to 2027 or later

      Sightline's estimate, as reported in February 2026. Power procurement, transformers and permits, not concrete, set the pace.

      E&E News - data center construction delays grow, report says (citing Sightline Climate) · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: 2027-02-12 · Legacy source/access date: 2026-02-24

    • GE Vernova gas turbines under contract, end-Q3 2026

      122 GW: 64 GW backlog + 58 GW slot reservations

      Up from 116 GW at end-Q2. Slot reservations are not firm orders. In July the company said new orders deliver in 2031, so long turbine lead times can delay projects that plan gas generation.

      GE Vernova - third quarter 2026 results · companyPublished: 2026-10-28 · Effective: not specified · Source checked: 2026-11-12 · Next review: 2027-01-31

    Capital

    Who is paying, and how

    • Top-5 hyperscaler capex forecast for 2026 (CreditSights, January 2026)

      $602 billion, +36%

      A forecast made before the 2026 earnings seasons. Most of it is data centers and the chips inside them.

      Data Center Knowledge - hyperscalers in 2026Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-15

    • 2026 capex after third-quarter results: Amazon, Alphabet, Meta, Microsoft and SpaceX (Business Insider tally)

      $803 billion to $828 billion

      Directional: a press tally of company guidance, and a different group of companies from the January forecast, so the two are not a like-for-like change. Amazon held about $220 billion; Microsoft guided to about $170 billion for the calendar year.

      Business Insider, republished by Hargreaves Lansdown - AI hyperscalers expected to finish the year spending $828 billion on capex · reportingPublished: 2026-10-30 · Effective: not specified · Source checked: 2026-11-12 · Next review: 2027-02-05

    • US data center construction, September 2026 (Census Bureau, annual rate, preliminary)

      $96.5 billion, up 90.3% year on year

      The Census table shows $96,462 million for September, up 8.6% from a revised $88,815 million in August and up from $50,700 million a year earlier. Shells and site power only; servers, racks, power plants and transmission are counted elsewhere.

      US Census Bureau - Value of Private Construction Put in Place, seasonally adjusted annual rate · regulatorPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: 2026-12-05 · Legacy source/access date: 2026-11-02

    • US data center investment, 2025 (S&P Global)

      $63.35 billion; private equity 72%

      This is a transaction-market measure; it does not establish the accounting treatment of any tenant's commitments.

      S&P Global - private equity sends US data center deals to a 5-year highPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-15

    • Largest private digital-infrastructure deal

      Aligned Data Centers, $40 billion

      AIP, BlackRock's GIP and MGX bought a developer, not a tenant - the shell is now the asset class.

      Aligned Data Centers - acquisition closesPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01

    • Stargate US sites by 2029 (Epoch AI)

      >9 GW across seven sites

      A reported development pipeline, including future phases, rather than delivered operating capacity.

      Epoch AI - where the US Stargate sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23

    • US data center industry contribution to government revenue (PwC)

      $66.2bn (2017) → $162.7bn (2023)

      The fiscal case the industry makes; set it beside the incentives below.

      Georgia Tech - who benefits? (citing PwC)Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09

    Follow the money · hypotheses

    Who is investing in which campuses and power deals, and why

    Who is in comes from the registers above: each campus's named backers and each energy deal's parties. Why they are in, and what a CFO should watch, is Koko's hypothesis, not a finding. It adds no number of its own.

    47 named backers across 28 campuses and 14 energy deals in this register. Policy records have no backers. A backer named in a source is not proof of the size of its stake.

    What CFOs should care about · Koko's hypothesis

    1. Power has moved from a facilities line to a strategic cost of AI. Ask every capacity provider where its electricity comes from, on what contract, and until when. See Hyperscalers, Power owners.
    2. Much of this capacity sits in joint ventures, leases and minimum commitments. Read guarantees and commitments notes before trusting reported leverage, yours or a counterparty's. See Private capital, AI labs, Developers.
    3. A few labs and hyperscalers anchor most of the demand. Counterparty concentration runs through developers, compute providers, lenders and power owners alike. See AI labs, Compute providers, Developers, Power owners.
    4. Vendors and sovereigns invest in their own customers. Revenue, pricing and allocation can be linked in ways a single contract does not show. See Chip and network vendors, Sovereigns and public lenders.

    Hyperscalers: buy certainty of delivery

    Meta, Microsoft, Google and Amazon fund their own campuses and sign for the power plants behind them.

    Who is in

    • 3 campuses · 5 energy deals · funds or owns, buys the output, funds developmentCompany hub
    • 2 campuses · 2 energy deals · funds or owns, buys the output, funds developmentCompany hub
    • 3 campuses · 1 energy deal · funds or owns, buys the outputCompany hub
    • 2 campuses · 1 energy deal · funds or owns, buys the outputCompany hub

    Hypothesis: why they are in

    They are paying for capacity that arrives on schedule. Cloud and model revenue waits on powered halls, and the grid cannot promise a date, so they fund the campus and contract the plant behind it, up to sponsoring new reactors. The adjacency spend is insurance on the core spend.

    What a CFO should watch

    • Server and GPU depreciation lives drive their reported margins. Compare each one's assumed useful life with the chip refresh cycle before reading their profitability.
    • Long-dated power contracts are purchase obligations. Read the commitments note, not the press release.
    • If you buy AI or cloud capacity from them, expect pricing that passes power and capacity costs through. Ask which campus serves you and what its delivery evidence says.

    What would change our mind: Capex guidance cut while campuses switch to leased capacity, or reactor sponsorships restructured into plain offtake.

    Records behind this read (9)

    AI labs: anchor the demand, rent the balance sheet

    OpenAI commits as tenant and takes stakes abroad; xAI is the exception that owns and powers its own campus.

    Who is in

    • 1 campus · 1 energy deal · funds or owns, owns or operates
    • 1 campus · funds or owns

    Hypothesis: why they are in

    Labs need more capacity than they can fund, so partners build and own while the lab signs the long-term commitment. Their tenancy is what makes a developer's or lender's deal bankable. xAI trades permitting risk for speed by building its own gas generation.

    What a CFO should watch

    • Counterparty concentration: a developer, provider or lender whose revenue rests on one lab carries that lab's funding risk.
    • Minimum-commitment and take-or-pay terms behave like debt to the payer even when they are not reported as debt.
    • Plans move. Abilene's dropped expansion shows a phase can disappear when financing and demand terms stall; ask who bears the cost.

    What would change our mind: Labs financing and owning campuses on their own balance sheets, or a lab renegotiating commitments without loss to its partners.

    Records behind this read (7)

    Compute providers: own the GPUs inside someone else's building

    Oracle owns the hardware at the Oracle-operated Stargate sites; Nscale co-owns Narvik, where Microsoft took the capacity.

    Who is in

    • 6 campuses · owns the hardware, funds or ownsCompany hub
    • 1 campus · 1 energy deal · funds or owns, owns or operates

    Hypothesis: why they are in

    Owning hardware in a developer's shell is the fastest way to sell capacity to a lab. It turns a software or telecom balance sheet into a capital-intensive one, and the bet is that contracted demand pays the hardware off before it ages.

    What a CFO should watch

    • Capital intensity and free cash flow move sharply for providers that used to be asset-light. Read cash flow, not bookings.
    • GPU residual value and obsolescence risk sit with whoever owns the hardware.
    • Contracted revenue disclosures show the backlog; check how much of it rests on one customer.

    What would change our mind: Hardware ownership shifting back to tenants or into financing vehicles, or backlog converting to revenue slower than hardware ages.

    Records behind this read (5)

    Developers: sell speed

    Crusoe, Vantage, STACK, Related Digital and the listed colocation majors assemble land, power and permits before the tenant arrives.

    Who is in

    • 3 campuses · funds or owns
    • 1 campus · funds or owns
    • 1 campus · funds or ownsCompany hub
    • 1 campus · funds or owns
    • 1 campus · funds or owns

    Hypothesis: why they are in

    A developer's edge is a site that can be energized sooner than a tenant could manage alone. The return depends on signing long leases with creditworthy anchors and on delivering when promised, which is where slips and local opposition bite.

    What a CFO should watch

    • Lease or service contract? The classification decides whether the capacity lands on your balance sheet.
    • When completions slip, delivery-date remedies matter more than headline price.
    • Community and permitting risk sits with the developer until it does not. Ask about litigation and settlement history at the site.

    What would change our mind: Tenants returning to self-build at scale, or developers taking sites forward without a signed anchor.

    Records behind this read (7)

    Private capital: rent the hyperscaler's credit

    Blue Owl, Primary Digital Infrastructure and Knighthead fund campuses directly; infrastructure funds buy the developers.

    Who is in

    • 2 campuses · funds or owns, joint-venture capitalCompany hub
    • 1 campus · reported backer
    • 1 campus · funds or owns

    Hypothesis: why they are in

    Infrastructure and private-credit funds want long, contracted cash flows with a hyperscaler or lab on the other side. A joint venture lets the tenant keep the capacity while sharing the capital, and the fund earns more than the tenant's own debt would pay.

    What a CFO should watch

    • Joint ventures and special purpose vehicles: consolidation is a judgment, not a given. Read the guarantees and any residual value support.
    • These structures cost more than corporate debt. Compare the all-in cost of capacity with owning it.
    • Refinancing risk rises if credit tightens before a campus is leased up and energized.

    What would change our mind: Fund-raising for digital infrastructure slowing, or new joint-venture terms shifting completion risk back to tenants.

    Records behind this read (5)

    Sovereigns and public lenders: treat compute as strategic infrastructure

    G42, MGX, Saudi Arabia's PIF, Bpifrance and Kazakhstan fund domestic capacity; the US Department of Energy and TVA backstop power.

    Who is in

    • 2 campuses · funds or owns
    • 2 energy deals · lends
    • 1 campus · funds or owns
    • 1 campus · funds or owns
    • 1 campus · funds or owns
    • 1 campus · funds or owns
    • 1 energy deal · buys the output

    Hypothesis: why they are in

    States want domestic AI capacity and a seat in global deals, so sovereign funds co-invest where a private return alone would not clear. Public lenders and utilities carry power risk, such as reactor restarts, that private capital will not take on its own.

    What a CFO should watch

    • Data residency and export-control terms can decide where a multinational is allowed to run AI workloads.
    • Public money carries conditions such as local content, jobs and reporting, and they flow down to suppliers and tenants.
    • A campus funded by one state is exposed to that state's policy and its relations with chip-exporting countries.

    What would change our mind: Export-control changes that strand overseas capacity, or sovereign funds pulling back from co-investment.

    Records behind this read (7)

    Conglomerates and telcos: turn land, power and networks into a position

    SoftBank, Foxconn, Reliance, Adani, Bharti Airtel and Aker bring sites, power, fiber or manufacturing.

    Who is in

    • 3 campuses · funds or owns
    • 1 campus · 1 energy deal · funds or owns, owns or operates
    • 1 campus · funds or owns
    • 1 campus · funds or owns
    • 1 campus · funds or owns
    • 1 campus · funds or owns
    • 1 campus · funds or owns

    Hypothesis: why they are in

    Groups that already hold the scarce inputs use them to buy into AI infrastructure rather than remain only customers of it. Hosting a hyperscaler or a lab also anchors their own power, telecom or industrial assets for years.

    What a CFO should watch

    • A partner with captive power or land can shorten delivery; confirm that the advantage is written into the contract.
    • Related-party flows inside a group can hide the economics of a single campus from outside readers.

    What would change our mind: Group partners exiting campus stakes once a hyperscaler can contract the same inputs directly.

    Records behind this read (6)

    Chip and network vendors: invest in their own demand

    NVIDIA and Cisco hold equity alongside sovereign and lab partners.

    Who is in

    Hypothesis: why they are in

    A stake in a customer's campus helps secure demand for the vendor's hardware and a say in where it lands. That can be sound strategy and still create circular revenue that is harder to read from the outside.

    What a CFO should watch

    • When a supplier also invests in your capacity, check pricing, allocation and exclusivity terms for linkage.
    • For investors and auditors: revenue from customers the vendor also funds deserves a separate look in quality-of-earnings work.

    What would change our mind: Vendors stepping back from equity as customers fund campuses on their own.

    Records behind this read (2)

    Power owners: firm, connected capacity becomes contracted infrastructure

    Constellation, Talen and Vistra sell existing nuclear output; Oklo, TerraPower, Kairos and X-energy build reactors; Entergy, Williams and EQT bring gas.

    Who is in

    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operates
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · supplies fuelCompany hub
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operates
    • 1 energy deal · owns or operates
    • 1 energy deal · owns or operates
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operates
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operatesCompany hub
    • 1 energy deal · owns or operates

    Hypothesis: why they are in

    Long contracts with hyperscalers turn merchant power into something closer to regulated infrastructure, and the scarce asset is firm capacity that is already connected. Restarts and existing reactors sell first because they are the fastest firm supply; new reactors and gas fill the gap later.

    What a CFO should watch

    • Electricity is becoming a larger and less predictable line in the cost of AI. Model it explicitly rather than inside a cloud price.
    • Utility rate cases are reallocating grid costs. Large-load tariffs can reach your own facilities even if you build no data center.
    • Firm power contracted now sets competitors' cost of AI for decades; ask your providers where their power comes from and for how long.

    What would change our mind: Grid connection timelines shortening, or efficiency gains flattening data center electricity demand.

    Records behind this read (7)
    Every backer and the records it is in
    BackerTypeCampusesEnergy dealsRegions
    MetaHyperscalersMeta Hyperion; Meta Prometheus; Meta LebanonDavis-Besse, Perry and Beaver Valley (Vistra); Oklo power campus, southern Ohio; TerraPower Natrium units (Meta-funded); Entergy gas plants for Hyperion; Behind-the-meter gas for PrometheusNorth America
    OracleCompute providersStargate Abilene; Stargate Shackelford County; Stargate Doña Ana (Project Jupiter); Stargate Port Washington (Lighthouse); Stargate Saline Township (The Barn); Stargate UAE (UAE–US AI Campus)NoneNorth America, Middle East & Africa
    Amazon (AWS)HyperscalersAmazon Project Rainier; AWS Peru regionSusquehanna Steam Electric Station; Cascade advanced reactor project (X-energy Xe-100)North America, Latin America
    MicrosoftHyperscalersMicrosoft Fairwater Wisconsin; Microsoft Fairwater Atlanta; Microsoft India South Central regionCrane Clean Energy Center (Three Mile Island Unit 1)North America, Asia-Pacific
    Google (Alphabet)HyperscalersGoogle Wilbarger County; Google AI Hub VisakhapatnamKairos Power Hermes 2North America, Asia-Pacific
    SoftBank GroupConglomerates and telcosStargate Milam County; Stargate Lordstown; Stargate UAE (UAE–US AI Campus)NoneNorth America, Middle East & Africa
    Vantage Data CentersDevelopersStargate Shackelford County; Stargate Port Washington (Lighthouse); Vantage Québec expansionNoneNorth America
    Aker ASAConglomerates and telcosNarvik AI gigafactory (ex-Stargate Norway)Narvik hydro supplyEurope
    Blue Owl CapitalPrivate capitalStargate Abilene; Meta HyperionNoneNorth America
    MGXSovereigns and public lendersStargate UAE (UAE–US AI Campus); Campus AI (MGX · Mistral) Île-de-FranceNoneMiddle East & Africa, Europe
    NscaleCompute providersNarvik AI gigafactory (ex-Stargate Norway)Narvik hydro supplyEurope
    NVIDIAChip and network vendorsStargate UAE (UAE–US AI Campus); Campus AI (MGX · Mistral) Île-de-FranceNoneMiddle East & Africa, Europe
    US Department of EnergySovereigns and public lendersNoneCrane Clean Energy Center (Three Mile Island Unit 1); Palisades restartNorth America
    xAI (SpaceX)AI labsxAI Colossus 2Colossus 2 gas turbinesNorth America
    Adani EnterprisesConglomerates and telcosGoogle AI Hub VisakhapatnamNoneAsia-Pacific
    Bharti AirtelConglomerates and telcosGoogle AI Hub VisakhapatnamNoneAsia-Pacific
    BpifranceSovereigns and public lendersCampus AI (MGX · Mistral) Île-de-FranceNoneEurope
    CiscoChip and network vendorsStargate UAE (UAE–US AI Campus)NoneMiddle East & Africa
    Constellation EnergyPower ownersNoneCrane Clean Energy Center (Three Mile Island Unit 1)North America
    CrusoeDevelopersStargate AbileneNoneNorth America
    Energy NorthwestPower ownersNoneCascade advanced reactor project (X-energy Xe-100)North America
    EntergyPower ownersNoneEntergy gas plants for HyperionNorth America
    EQTPower ownersNoneHomer City gas generationNorth America
    EquinixDevelopersEquinix SP7 São PauloNoneLatin America
    ExxonMobilPower ownersNoneExxonMobil–NextEra gas with carbon captureNorth America
    FoxconnConglomerates and telcosStargate LordstownNoneNorth America
    G42Sovereigns and public lendersStargate UAE (UAE–US AI Campus)NoneMiddle East & Africa
    Government of KazakhstanSovereigns and public lendersData Center Valley, EkibastuzNoneAsia-Pacific
    HoltecPower ownersNonePalisades restartNorth America
    Homer City RedevelopmentPower ownersNoneHomer City gas generationNorth America
    Kairos PowerPower ownersNoneKairos Power Hermes 2North America
    Knighthead CapitalPrivate capitalHomer City Energy CampusNoneNorth America
    NextEraPower ownersNoneExxonMobil–NextEra gas with carbon captureNorth America
    OkloPower ownersNoneOklo power campus, southern OhioNorth America
    OpenAIAI labsStargate UAE (UAE–US AI Campus)NoneMiddle East & Africa
    Primary Digital InfrastructurePrivate capitalStargate AbileneNoneNorth America
    Public Investment Fund (Saudi Arabia)Sovereigns and public lendersHumain AI Data CentersNoneMiddle East & Africa
    Related DigitalDevelopersStargate Saline Township (The Barn)NoneNorth America
    Reliance IndustriesConglomerates and telcosReliance–Meta JamnagarNoneAsia-Pacific
    SoftBank Corp.Conglomerates and telcosSoftBank Tomakomai AI data centerNoneAsia-Pacific
    STACK InfrastructureDevelopersStargate Doña Ana (Project Jupiter)NoneNorth America
    Talen EnergyPower ownersNoneSusquehanna Steam Electric StationNorth America
    Tennessee Valley AuthoritySovereigns and public lendersNoneKairos Power Hermes 2North America
    TerraPowerPower ownersNoneTerraPower Natrium units (Meta-funded)North America
    VistraPower ownersNoneDavis-Besse, Perry and Beaver Valley (Vistra)North America
    WilliamsPower ownersNoneBehind-the-meter gas for PrometheusNorth America
    X-energyPower ownersNoneCascade advanced reactor project (X-energy Xe-100)North America

    Communities

    What a town gets, and what it gives up

    Reported measurements, estimates and commitments. Their source populations and dates differ; they are not universal forecasts.

    • A typical site (Georgia Tech)

      ~1,500 to build, under 200 to run

      The jobs are in the construction phase; permanent headcount is small relative to the power draw.

      Georgia Tech - Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09

    • Local electricity price after a large facility enters (Georgia Tech)

      about +5%

      Where the effect can be measured cleanly it is real and modest; the PJM figure below is the system-wide version.

      Georgia Tech - Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09

    • PJM capacity costs attributed mainly to data center demand (market monitor)

      $23.1 billion across three auctions

      Covers the 2025/26 to 2027/28 delivery years. Customers fund it through utilities and suppliers; it is not a line on every bill and says nothing about other regions.

      Fortune - data centers have already hiked electricity prices by $23 billionPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: 2027-01-12 · Legacy source/access date: 2026-07-14

    • US data center on-site water use, 2023 (Lawrence Berkeley National Laboratory for DOE)

      ~17 billion gallons

      Cooling water used at the sites themselves. A 2028 projection shown here before November 12, 2026 was removed because it could not be traced to the report.

      LBNL - 2024 United States Data Center Energy Usage Report · regulatorPublished: 2024-12-20 · Effective: not specified · Source checked: 2026-11-12 · Next review: 2027-05-12

    • Ohio data center tax exemptions, 2025

      $1.6 billion, 11× the projection

      Incentives scale with the capex they were written for, not the one that arrived.

      Georgia Tech - Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09

    • Loudoun County, Virginia property taxes over a decade

      cut ~30%, on ~250 data centers

      A reported local fiscal outcome; incentives, tax structures and infrastructure costs differ elsewhere.

      Georgia Tech - Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09

    • States offering data center tax incentives (NCSL)

      at least 38

      Incentive competition is national; at least 10 states forgo more than $100 million a year (Good Jobs First).

      Georgia Tech - Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09

    Backlash and policy

    Pauses, directives, lawsuits and connection rules

    Newest first. A count is a count by the outlet named, not Koko's.

    1. Measured United States
      SAVRN's tracker lists 1,299 local governments with a data center measure on record. It counts proposed, in-force, paused and failed measures, so it is far broader than the 300+ count of bans and moratoriums below and cannot be compared with it. (SAVRN — data center moratorium tracker update, November 3, 2026 · Third-party estimatePublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-11-03)
    2. Directive Texas
      Governor Abbott paused approval of new data center grid connections in the ERCOT region on August 3, 2026 until regulators audit the applicants. On September 21 he told the state environmental agency to hold their permits too. Projects that bring their own power are exempt. (The Texas Tribune - Abbott pauses data center permits pending water and power review · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-09-21)
    3. Moratorium New York
      Executive Order 62 paused new data centers of 50 MW or more for up to one year, the first statewide moratorium; Pennsylvania, Michigan and South Carolina considering pauses. (Resilience - the data center backlash that's uniting AmericaPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-23)
    4. Measured United States
      More than 300 cities, towns and counties with bans or moratoriums on hyperscale data centers (a count by The Information). (TIME - Community backlash to AI data centers is growing across the U.S.Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-22)
    5. Measured United States
      75 major projects worth more than $130 billion delayed or canceled in the first three months of 2026, in part due to organized local opposition. (TIME - Community backlash to AI data centers is growing across the U.S.Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-22)
    6. Moratorium Seattle · Denver
      Seattle became the largest US city with a data center moratorium; Denver's council unanimously approved a one-year pause while it drafts rules. (Stateline - more cities are pressing pause on data centersPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-28)
    7. Rejection Sangamon County, Illinois
      A proposed six-month moratorium failed 5–3 in committee - moratoria do not always pass. (Stateline - more cities are pressing pausePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-28)
    8. Lawsuit Memphis / Southaven
      The NAACP, represented by SELC and Earthjustice, sued xAI in federal court on April 14, 2026. The suit says 27 gas turbines at Colossus 2 ran without Clean Air Act permits. xAI says it complies with the law. (SELC - civil rights group sues xAI over data center power plant pollution · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2026-04-14)
    9. Connection policy Ireland
      Ireland's regulator replaced its moratorium-style approach with site-by-site tests. A new data center of 10 MVA or more must bring generation or storage equal to its grid import, and meet 80% of annual demand from additional Irish renewables after a six-year glide path. (Philip Lee - Ireland's new CRU Large Energy User connection policy · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2025-12-22)
    10. Rejection Saline Township, Michigan
      The township board voted against rezoning the Stargate site in September 2025. The developer sued, and the township settled in October 2025. A resident challenged the settlement in court in December 2025. (ClickOnDetroit - Saline Township resident files lawsuit to stop data center project · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2025-12-14)
    11. Moratorium Amsterdam region
      A national rule bars new data centers over 10 hectares with a 70 MW connection outside two designated areas, in force since January 1, 2024. Facilities already built or permitted are not covered. (Greenberg Traurig - challenges in the Dutch data center market · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2024-03-04)

    Who enables it

    The chain, end to end

    Anchors, chips, builders, power, equipment and capital. A row with a figure links its source; a row without one carries its role only. Listed companies open on the company hub.

    Anchor tenants and labs

    • OpenAI

      Stargate's tenant across seven US sites and the UAE; the demand signal behind Oracle, Crusoe, Vantage and SoftBank's builds.

      Epoch AI projects the seven US Stargate sites at more than 9 GW by 2029. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • Meta

      Builds its own campuses (Hyperion, Prometheus, Lebanon) and signs the largest corporate nuclear deals.

      Up to 6.6 GW of nuclear agreements with Vistra, TerraPower and Oklo (January 2026). (Axios — Meta nuclear dealsPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-09)

    • Microsoft

      Fairwater in Wisconsin and Atlanta; took over the Narvik capacity OpenAI dropped.

      A 20-year PPA for the Crane (Three Mile Island) restart. (NRC — Crane restart environmental findingPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-09-30)

    • Amazon (AWS)

      Project Rainier for Anthropic; the largest nuclear PPA with Talen; funds X-energy's Cascade reactors.

      1,920 MW from Susquehanna through 2042. (Talen Energy — expanded Amazon agreementPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-06-11)

    • Google (Alphabet)

      Visakhapatnam, Texas and Minnesota campuses; the first Gen IV reactor PPA via TVA.

      $15 billion over 2026–2030 for the 1 GW Visakhapatnam hub. (Google India blog — AI HubPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-28)

    • xAI (SpaceX)

      Colossus in Memphis, built largely off-grid on gas turbines.

      ~1 GW live, 2 GW targeted. (Techzine — xAI expands Colossus to 2 GWPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-06-01)

    • Anthropic

      Rainier's tenant on AWS; Fluidstack sites in New York and Texas announced November 2025.

      $50 billion of Fluidstack sites announced. (AP via Yahoo Finance — Anthropic announces $50 billion data center plan · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2025-11-12)

    • G42 · MGX

      Abu Dhabi's AI champion and its investment arm: Stargate UAE, Campus AI France, the Aligned consortium.

      Co-acquirer of Aligned Data Centers at a $40 billion enterprise value. (Aligned Data Centers — AIP, MGX and BlackRock's GIP close $40B acquisitionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01)

    Chips and compute

    • NVIDIA

      GB200/GB300 and Rubin GPUs in nearly every campus here; an equity partner in Stargate UAE and the Aligned consortium.

      Abilene is built for more than 450,000 GB200 GPUs; Narvik takes 30,000 Rubin GPUs in 2027. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • AMD

      Humain's accelerator partner; an OpenAI supply agreement.

      Role only — no figure read for this row.

    • Amazon Trainium

      Amazon's own training chip; Rainier runs ~500,000 Trainium2.

      Rainier is Trainium-only, not NVIDIA. (SiliconANGLE — AWS opens $11B Project Rainier campus built for Anthropic · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2025-10-29)

    • Broadcom

      Custom accelerators and networking for the hyperscalers; an OpenAI custom-chip partner.

      Role only — no figure read for this row.

    • Groq

      Inference silicon for Aramco Digital's announced 500 MW Saudi facility.

      Role only — no figure read for this row.

    Developers, builders and operators

    • Crusoe

      Developer of Stargate Abilene.

      357 full-time jobs committed at Abilene once construction ends. (Programs.com — data center employment statisticsPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-08-01)

    • Vantage Data Centers

      Developer of the Shackelford County and Port Washington Stargate sites; Québec campus.

      Two Stargate sites totalling 3.3 GW projected. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • STACK Infrastructure

      Developer of Project Jupiter, Doña Ana County.

      2.2 GW projected, Q4 2028. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • Related Digital

      Developer of The Barn, Saline Township.

      1.4 GW projected after litigation and a settlement with the township. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • SB Energy (SoftBank)

      Developer and power provider for the Milam County Stargate site.

      A "fast-build" site with SoftBank-owned hardware. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • Khazna Data Centers

      Builder of the Stargate UAE cluster for G42.

      First 200 MW due in 2026. (Gulf News — Stargate UAE first phasePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-10)

    • Nscale · Aker

      Joint-venture developer of the Narvik gigafactory.

      Microsoft contracted 30,000 Rubin GPUs there for 2027. (DCD — Microsoft contracts 30,000 Rubin GPUs from NscalePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-15)

    • Aligned Data Centers

      Hyperscale developer bought by AIP, GIP and MGX.

      $40 billion enterprise value plus $5 billion of committed growth capital. (Aligned Data Centers — AIP, MGX and BlackRock's GIP close $40B acquisitionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01)

    • Oracle

      Operates five of the seven US Stargate sites and owns their hardware; OpenAI's largest compute supplier.

      Owns the hardware at Abilene, Shackelford, Doña Ana, Port Washington and Saline. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)

    • Equinix · Digital Realty

      The two listed colocation majors; smaller AI-ready builds worldwide.

      Role only — no figure read for this row.

    • AdaniConneX · Nxtra (Airtel)

      Build the Visakhapatnam AI hub for Google.

      Role only — no figure read for this row.

    Power: generation, fuel and grid

    • Constellation Energy

      Largest US nuclear operator; restarting Crane for Microsoft.

      835 MW restart targeted 2027 with a $1 billion DOE loan. (Constellation — Crane one year laterPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-09-19)

    • Vistra

      Ohio and Pennsylvania nuclear output and uprates sold to Meta.

      2,176 MW plus 433 MW of uprates under a 20-year PPA. (ANS — the Meta–Vistra dealPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-12)

    • Talen Energy

      Susquehanna output to Amazon.

      About $18 billion of revenue expected over the contract. (Talen Energy — expanded Amazon agreementPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-06-11)

    • Holtec

      Restarting Palisades; SMR developer; filed for an IPO in 2026.

      Restart targeted 2026, ahead of a March 2027 counterparty date. (Holtec — Form S-1Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-08-15)

    • Oklo

      Advanced-reactor developer; a 1.2 GW campus for Meta in Ohio.

      Role only — no figure read for this row.

    • TerraPower

      Natrium sodium fast reactors; up to eight units funded by Meta.

      Role only — no figure read for this row.

    • Kairos Power

      Hermes 2 molten-salt reactor for TVA and Google.

      50 MW from 2030. (Kairos Power — Google, Kairos, TVAPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-08-18)

    • X-energy · Energy Northwest

      Four Xe-100 reactors in Washington, Amazon-funded.

      Role only — no figure read for this row.

    • NuScale

      The only NRC-certified SMR design; shares down 53% year to date by October 2026.

      Role only — no figure read for this row.

    • Entergy

      Builds three gas plants for Hyperion in Louisiana.

      Role only — no figure read for this row.

    • Williams

      Behind-the-meter gas for Meta Prometheus.

      Role only — no figure read for this row.

    • EQT

      Gas supply to the Homer City campus.

      Role only — no figure read for this row.

    • NextEra Energy

      Gas-with-capture project with ExxonMobil; the Duane Arnold restart.

      Role only — no figure read for this row.

    • Tennessee Valley Authority

      Grid for Colossus and the Hermes 2 offtaker.

      Role only — no figure read for this row.

    Turbines, transformers, cooling

    • GE Vernova

      Heavy-duty gas turbines — the pacing item for behind-the-meter power.

      122 GW of gas turbines under contract at end-Q3 2026: 64 GW of backlog and 58 GW of slot reservations, up from 116 GW at end-Q2. (GE Vernova — third quarter 2026 results · companyPublished: 2026-10-28 · Effective: not specified · Source checked: 2026-11-12 · Next review: 2027-01-31)

    • Siemens Energy

      Gas turbines and grid equipment; the other Western turbine supplier.

      Role only — no figure read for this row.

    • Hitachi Energy

      Large power transformers — the other long-lead item.

      Role only — no figure read for this row.

    • Bloom Energy

      Fuel cells for on-site power.

      Role only — no figure read for this row.

    • Vertiv · Schneider Electric · Eaton

      Liquid cooling, power distribution and switchgear inside the hall.

      Role only — no figure read for this row.

    • Foxconn

      Rack and server integration; JV partner at Lordstown; Fairwater sits on its former Wisconsin site.

      Role only — no figure read for this row.

    Capital: funds, SPVs and lenders

    • Blue Owl Capital

      Financed Hyperion through a joint-venture SPV; a Stargate Abilene investor.

      Hyperion JV reported at ~$27 billion of development. (DCD — Meta forms $27 billion joint venture with Blue Owl for Hyperion · reportingPublished: not distinguished · Effective: not specified · Source checked: 2026-11-12 · Next review: not scheduled · Legacy source/access date: 2025-10-21)

    • AI Infrastructure Partnership (AIP)

      BlackRock, Microsoft, MGX, NVIDIA and xAI's infrastructure fund.

      Aligned was its first investment; a $30 billion equity target supporting up to $100 billion with debt. (Aligned Data Centers — AIP, MGX and BlackRock's GIP close $40B acquisitionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01)

    • BlackRock · Global Infrastructure Partners

      Co-acquirer of Aligned.

      Role only — no figure read for this row.

    • SoftBank Group

      Stargate's financing partner; owns the Milam County and Lordstown hardware.

      Role only — no figure read for this row.

    • Macquarie Asset Management

      Sold Aligned to the consortium.

      Role only — no figure read for this row.

    • Blackstone · Brookfield · KKR

      The private-capital owners of QTS and the European and Asian colocation platforms.

      Private equity was 72% of the $63.35 billion invested in US data centers in 2025. (S&P Global — private equity sends US data center deals to a 5-year highPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-15)

    • Bpifrance

      French state investor in the Campus AI project.

      Role only — no figure read for this row.

    • US Department of Energy loan office

      Restart lender.

      $1 billion to Constellation for Crane. (Constellation — Crane one year laterPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-09-19)

    Koko's PoV

    Six reads of the map

    Koko's view. Each rests on the figures above and adds no number of its own.

    1. 1.Power delivery belongs in the AI capacity decision.

      The Crane restart record describes a disputed connection timetable; the equipment figures describe long lead times. These examples suggest delivery risk, but do not establish that every on-time campus has its own generation.

      For: CFOs and technology leaders: verify a provider's delivery milestones and contingency capacity before committing spend.

    2. 2.Community acceptance depends on who bears the costs and receives the benefits.

      The community register includes reported rate effects, water concerns, job commitments and tax incentives. Their relative importance varies by jurisdiction; a local study is not a universal forecast.

      For: Developers and advisers: test cost allocation and community commitments against the local evidence.

    3. 3.Financing terms can matter as much as announced campus size.

      The Hyperion joint venture and Aligned acquisition show different ways to finance infrastructure. A JV alone does not establish off-balance-sheet accounting or transfer all risk from a tenant.

      For: Treasurers and investors: review lease obligations, guarantees, consolidation judgments and completion conditions.

    4. 4.Separate construction employment from lasting local benefits.

      Abilene and Hyperion report different construction and permanent commitments. Local tax receipts also depend on incentives and ownership terms, so one county's outcome should not be generalized.

      For: Local governments and advisers: reconcile jobs, incentive costs and fiscal benefits over the project lifecycle.

    5. 5.Power arrangements have different delivery and emissions profiles.

      Colossus has reported gas generation; Hyperion is under construction with gas-backed supply planned. Nuclear restarts, existing-plant PPAs and new reactors have different milestones. A contract does not prove physical supply or an achieved carbon outcome.

      For: Energy and sustainability leads: check asset status, connection evidence, hourly supply and accounting boundaries.

    6. 6.Infrastructure creates several distinct advisory needs.

      The register points to procurement, project finance, permitting, community agreements, reporting and supply-chain questions. These are potential engagements, not evidence of a quantified market or a mandate.

      For: Partner / MD: connect a specific client exposure to a sourced development and a concrete diligence question.

    Opportunities · directional

    Where the work is

    Koko's reading of where the demand lands, for companies and for professional-services firms. Directional, not a sized market.

    For companies

    • AI capacity sourcing: own, colocate or rent

      Signal: 2026 hyperscaler capex forecasts above $600 billion and 30–50% of 2026 completions slipping.

      A capacity plan that prices cloud, colocation and dedicated builds against the model portfolio, with power as the binding constraint.

      On Koko: AI Stack Economics

    • Energy procurement for AI load

      Signal: Nuclear PPAs from 2027, turbines sold out to 2031, Ireland's self-supply rule.

      PPA and behind-the-meter options, interconnection timing, and what the carbon ledger says to investors.

      On Koko: Build a power-procurement question in Ask Koko

    • Sovereign and regional AI capacity

      Signal: Stargate UAE, Narvik, Visakhapatnam, Campus AI France, Ekibastuz.

      Data residency and export-control-aware placement for multinational AI workloads.

      On Koko: TMT Daily

    • Supplier and customer exposure to the build-out

      Signal: GE Vernova, Vistra, Constellation, Talen, Oracle and the colocation majors each carry a sourced hook here.

      Read the operators and enablers on this page through their own filings.

      On Koko: Company hub

    For professional-services firms

    • Site selection and incentive negotiation

      Signal: At least 38 states with incentives; Ohio's $1.6 billion overrun; 300+ local pauses by July 2026.

      Incentive modeling, abatement and sales-tax exemption structuring, and the community benefit agreement that gets a vote through.

      On Koko: Transform suite

    • Power procurement and rate-case support

      Signal: Entergy's three plants for one customer; PJM's $23 billion; CRU's self-supply rule.

      PPA structuring, cost-allocation testimony, interconnection strategy and the tariff work utilities now run for single customers.

      On Koko: Transform suite

    • Project finance, SPVs and transaction advisory

      Signal: Blue Owl–Meta, Aligned at $40 billion, private equity at 72% of deals.

      JV and SPV structuring, lease accounting, debt capacity, buy-side diligence on shells and power.

      On Koko: Accounting & Tax Watch

    • Energy, water and emissions assurance

      Signal: DOE water figures, EU reporting rules, the Colossus permit suit.

      Metered reporting, PUE and water assurance, and the controls behind the sustainability claims in an offering memorandum.

      On Koko: Internal Control Screen

    • Supply chain and construction cost control

      Signal: Turbines on a three-year lead, transformers behind them, a construction pace near $96 billion a year.

      Procurement strategy for long-lead equipment, schedule risk, and owner's-engineer cost control.

      On Koko: Process Architecture Studio

    Related news

    The build-out in Koko's corpus

    Stories about data centers, power deals and the grid from the sources Koko reads every day.

    Loading related news...

    Learn

    New to this?

    How a Data Center Gets Built walks the six stages from site to operation, who is involved at each, how long they take and what stops them, with the vocabulary in plain words. Ask the map a question in Ask Koko.