    How a Data Center Gets Built

    Six stages from a field with a substation to a campus training models — who is involved, how long each takes, what stops it, and the words people use.

    Open the God's-eye map of every campus →

    Every example below is a real campus on Koko's Data Center Eye View, where its full record and sources live.

    The lifecycle

    Six stages, end to end

    1. Stage 1

      Site and power

      Where is there land, water, fibre and, above all, power?

      Who is involved
      Developer, utility, landowners, state economic-development office
      How long
      Months to years; the interconnection queue sets it
      What stops it
      No grid capacity; a moratorium; a water fight
      On the map
      Stargate Saline Township (The Barn) — rejected by the township, litigated, settled
    2. Stage 2

      Tenant, capital and incentives

      Who will lease it, who funds it, what does the state give up?

      Who is involved
      Anchor tenant, fund or SPV, lenders, state and county
      How long
      Runs alongside stage 1
      What stops it
      Financing and demand forecasts move — Abilene's 600 MW expansion was dropped this way
      On the map
      Meta Hyperion — a ~$27 billion Blue Owl JV, three gas plants approved in phases
    3. Stage 3

      Permits and the public

      Air, water, zoning, rate cases — and the vote.

      Who is involved
      Regulators (PSC, EPA/state air, planning boards), residents, advocacy groups
      How long
      Months; longer where contested
      What stops it
      A permit suit (Colossus), a local pause (300+ jurisdictions), a statewide order (New York)
      On the map
      xAI Colossus 2 — turbines first, Clean Air Act suit after
    4. Stage 4

      Build the shell and the power

      Concrete, substations, turbines or a reactor restart.

      Who is involved
      EPC contractors, turbine and transformer suppliers, utilities
      How long
      ~12–24 months for a building; three years for a turbine order; 2027–2035 for nuclear
      What stops it
      Equipment lead times — GE Vernova's book runs to 2031
      On the map
      Stargate Doña Ana (Project Jupiter) — foundations under way, Q4 2028
    5. Stage 5

      Fit out the hall

      Racks, liquid cooling, networking, and hundreds of thousands of GPUs.

      Who is involved
      Chip vendors, integrators, the tenant's own engineers
      How long
      Weeks per building once the shell is powered
      What stops it
      Chip allocation and export controls
      On the map
      Microsoft Fairwater Atlanta — 140 kW racks, no UPS, no generators
    6. Stage 6

      Operate and expand

      Run it, measure it, and start the next phase.

      Who is involved
      Operator, utility and permanent staff whose size depends on the site and service model
      How long
      Decades; expansions every 1–2 years
      What stops it
      Rate shock and community fatigue — the Phase 2 fights
      On the map
      Amazon Project Rainier — 7 of ~30 buildings live; a $15 billion Phase 2 met zoning pushback

    Who is who

    The six layers of the chain

    Every company on the map sits in one of these layers.

    • Anchor tenants and labs

      OpenAI · Meta · Microsoft · Amazon (AWS) · Google (Alphabet) · xAI (SpaceX) · Anthropic · G42 · MGX

    • Chips and compute

      NVIDIA · AMD · Amazon Trainium · Broadcom · Groq

    • Developers, builders and operators

      Crusoe · Vantage Data Centers · STACK Infrastructure · Related Digital · SB Energy (SoftBank) · Khazna Data Centers · Nscale · Aker · Aligned Data Centers · Oracle · Equinix · Digital Realty · AdaniConneX · Nxtra (Airtel)

    • Power: generation, fuel and grid

      Constellation Energy · Vistra · Talen Energy · Holtec · Oklo · TerraPower · Kairos Power · X-energy · Energy Northwest · NuScale · Entergy · Williams · EQT · NextEra Energy · Tennessee Valley Authority

    • Turbines, transformers, cooling

      GE Vernova · Siemens Energy · Hitachi Energy · Bloom Energy · Vertiv · Schneider Electric · Eaton · Foxconn

    • Capital: funds, SPVs and lenders

      Blue Owl Capital · AI Infrastructure Partnership (AIP) · BlackRock · Global Infrastructure Partners · SoftBank Group · Macquarie Asset Management · Blackstone · Brookfield · KKR · Bpifrance · US Department of Energy loan office

    Vocabulary

    The words, in plain English

    MW / GW
    Megawatts and gigawatts of power. A gigawatt is roughly the output of one large nuclear reactor, or the draw of about a million US homes.
    Facility power vs IT power
    Facility power is the whole campus's draw; IT power is what the servers see. The gap is cooling and conversion. Sources rarely say which they mean.
    PUE
    Power usage effectiveness: facility power divided by IT power. 1.2 means 20% overhead.
    PPA
    Power purchase agreement: a long-term contract to buy a plant's output at an agreed price, often 20 years. The nuclear deals here are PPAs.
    Behind the meter
    Generation on the customer side of a meter. Delivery still depends on equipment, permits and operating arrangements; it does not imply a fast or approved connection.
    Front of the meter
    Power delivered through the grid under a contract. Talen and Amazon restructured their deal this way to avoid FERC approval.
    Interconnection queue
    Processes to study new generation or load connections. Generator queues and large-load studies are different; neither alone proves power available to a campus.
    SMR
    Small modular reactor: a factory-built reactor of tens to a few hundred megawatts. None supplying a data center is operating yet; Hermes 2 is scheduled for 2030.
    Restart
    Returning a closed reactor to service — Crane (Three Mile Island) and Palisades. Faster than a new build, still measured in years.
    Uprate
    Raising an existing reactor's licensed output; Vistra's deal with Meta includes 433 MW of them.
    SPV / JV
    A special purpose vehicle or joint venture that owns the campus so the tenant leases rather than builds — how Hyperion is financed.
    Moratorium
    A temporary ban on approving new projects while rules are written; more than 300 US jurisdictions have one.
    Community benefit agreement
    A negotiated package — jobs, local hiring, water limits, payments — exchanged for local approval.
    Hyperscaler
    The largest cloud operators — Amazon, Microsoft, Google, Meta, Oracle — building at gigawatt scale.