Koko's Data Center Eye View
Selected AI infrastructure, explained for professional decisions: campuses, energy arrangements, evidence and delivery questions.
AI infrastructure intelligence
Your professional briefing
What changed · October 18
Koko now separates power bases, qualifies estimates and flags evidence gaps. These are editorial changes, not new campus commissioning reports.
Inspect the change logWhy it matters
Capacity ambitions and delivery dates are different inputs to an AI investment case.
What to investigate next
Stress-test start dates, take-or-pay commitments and fallback capacity before approving spend.
The briefing follows your selection, comparison or energy/grid mode. The economics tool requires your workload and pricing assumptions; campus MW is not imported as a price.
Coverage: 29 selected named AI campuses and 17 energy assets or policies. This editorial sample prioritizes major AI developments with public reporting; it is not a census. Empty map areas do not mean no infrastructure. Legacy register snapshot: 2026-10-15; individual source and review dates vary.
Filter the evidence
Campus filters affect map, register, comparisons and brief. Energy type filters energy records only; region applies to both. Target dates filter cited projections, not historical operating status. Missing dated milestones are excluded when a date filter is active.
The God's-eye view
Campuses, energy arrangements and regional context
Drag to move, pinch or Ctrl + scroll to zoom, or search. Clusters split as you close in; tap a pin for its record. The register below is the same data as a table.
Interactive map, centred near 0.0°N 0.0°E, zoom 1.0×. Arrow keys pan, plus and minus zoom, zero resets. Every place on the map is also in the register below.
0.0°N 0.0°E, zoom 1.0×
Map legend · full build
- Operating
- Under construction
- Planned
- Announced
- Stalled or cut back
Circles: campuses. Diamonds: energy/policy. Hollow: unknown or equal sizing. Cluster numbers count places. Power bases vary; energy MW is not campus supply.
2 selected energy records have undisclosed locations and appear only in the register. Regional policy markers are reference locations, not facility sites.
- World · campuses
- 29
- Operating
- 6
- Under construction
- 17
- Planned
- 4
- Announced
- 2
- Stalled or cut back
- 0
Filtered register · 29 selected campuses
facility power
9.3 GW
Full-build figures · 6/7 records sized
Reported operating: 300 MW
Operating basis recorded here for 7/29 selected records
IT power
2 GW
Full-build figures · 1/1 records sized
Reported operating: not stated
Operating basis recorded here for 0/29 selected records
basis not stated
26.1 GW
Full-build figures · 19/21 records sized
Reported operating: 1.2 GW
Operating basis recorded here for 2/29 selected records
Snapshot 2026-10-15; metric dates vary. Full build includes projections and estimates, not demand or energy use. 3 exact full-build values unknown. Bases are not added together; no assumed PUE conversion. An operating campus can still have future phases.
Global coverage · all selected records
29 campuses · 17 energy assets and policies.
Global register · 29 selected campuses
facility power
9.3 GW
Full-build figures · 6/7 records sized
Reported operating: 300 MW
Operating basis recorded here for 7/29 selected records
IT power
2 GW
Full-build figures · 1/1 records sized
Reported operating: not stated
Operating basis recorded here for 0/29 selected records
basis not stated
26.1 GW
Full-build figures · 19/21 records sized
Reported operating: 1.2 GW
Operating basis recorded here for 2/29 selected records
Snapshot 2026-10-15; metric dates vary. Full build includes projections and estimates, not demand or energy use. 3 exact full-build values unknown. Bases are not added together; no assumed PUE conversion. An operating campus can still have future phases.
The register
Selected campuses and energy records
Snapshot 2026-10-15. Targets, reported operation and full build are different phases; sources and evidence gaps open with each record. Select a row to view its map detail.
| Site | For | Status | Full build | Operating | Power | Timing |
|---|---|---|---|---|---|---|
New Carlisle, Indiana, United States | Anthropic (on AWS) | Operating | 2.2 GW basis not stated | not stated basis not stated | Grid (Indiana Michigan Power); outside-air cooling October to March per AWS. | Operational October 2025 with 7 of ~30 planned buildings; 2.2 GW at full build. |
Lima, Peru | Amazon Web Services | Announced | 40 MW basis not stated | not stated basis not stated | Not stated. | Announced. |
Seine-et-Marne, France | Mistral AI and others | Planned | 1.4 GW basis not stated | not stated basis not stated | France's nuclear-heavy grid is the pitch. | Planned. |
Pavlodar Region, Kazakhstan | Kazakhstan Ministry of AI and Digital Development | Under construction | 1 GW basis not stated | not stated basis not stated | Ekibastuz is Kazakhstan's coal-power hub. | Under construction. |
London / Slough, United Kingdom | Multi-tenant | Planned | 300 MW basis not stated | not stated basis not stated | Grid; UK industrial power prices are the stated constraint. | Planned. |
São Paulo, Brazil | Multi-tenant | Planned | 14 MW basis not stated | not stated basis not stated | Grid (largely hydro). | Planned. |
Visakhapatnam, Andhra Pradesh, India | Under construction | 1 GW basis not stated | not stated basis not stated | Adani's renewable portfolio is the stated supply; an international subsea cable landing is part of the plan. | Groundbreaking 28 April 2026; the $15 billion runs 2026–2030. | |
Wilbarger County, Texas, United States | Under construction | not stated basis not stated | not stated basis not stated | AES named as the power partner. | Under construction. | |
Homer City, Pennsylvania, United States | Not yet named | Under construction | 4.5 GW basis not stated | not stated basis not stated | Seven gas generating units on the site of the former coal plant, 4.4–4.5 GW, supplied by EQT. | Construction began 2025. |
Riyadh and Dammam, Saudi Arabia | Humain (PIF) | Under construction | 200 MW basis not stated | not stated basis not stated | Not stated. | Under construction. |
Richland Parish, Louisiana, United States | Meta | Under construction | 5 GW basis not stated | not stated basis not stated | Three new Entergy gas plants; Phase I power approved by the Louisiana PSC, the Phase II expansion package under review. | First phase expected online 2028; full build-out reported to run to 2030. |
Lebanon, Indiana, United States | Meta | Under construction | 1 GW basis not stated | not stated basis not stated | Not stated. | Groundbreaking February 2026. |
New Albany, Ohio, United States | Meta | Under construction | 1 GW basis not stated | not stated basis not stated | Behind-the-meter natural gas built with Williams; Meta's January 2026 Vistra and Oklo nuclear agreements are framed around this cluster. | Meta said it comes online in 2026; a "tents over buildings" design chosen for speed. |
Atlanta, Georgia, United States | Microsoft (OpenAI workloads) | Operating | not stated basis not stated | not stated basis not stated | Grid; designed with no UPS or generator sets, ~140 kW per rack. | Online November 2025. |
Mount Pleasant, Wisconsin, United States | Microsoft (OpenAI workloads) | Operating | 2 GW basis not stated | not stated basis not stated | Grid (We Energies); closed-loop liquid cooling. | First facility reported fully operational June 2026; the adjacent second facility reported for 2028; Nadella: "scale to two gigawatts". |
Hyderabad, India | Microsoft | Under construction | 600 MW basis not stated | not stated basis not stated | Not stated. | Go-live mid-2026. |
Kvandal, Narvik, Norway | Microsoft (replacing OpenAI) | Under construction | 230 MW basis not stated | not stated basis not stated | 100% renewable (hydro) above the Arctic Circle. | First 230 MW phase targeted for H2 2026 (aggregator figure); Microsoft's 30,000 NVIDIA Rubin GPUs delivered in 2027; a 520 MW longer-term plan. |
Jamnagar, Gujarat, India | Meta (lessee) | Planned | 168 MW basis not stated | not stated basis not stated | Reliance's Jamnagar renewable and gas complex. | Delivery within two years of June 2026. |
Tomakomai, Hokkaido, Japan | SoftBank Corp. | Under construction | 300 MW basis not stated | not stated basis not stated | Hokkaido renewables are the stated pitch. | Under construction. |
Abilene, Texas, United States | OpenAI (Oracle-operated) | Operating | 1.2 GW facility power | 300 MW facility power | Grid plus on-site gas turbines; the campus sits beside a wind farm. Figures are total facility power. | First phase live September 2025; four of eight buildings reported operating; full 1.2 GW projected Q4 2026. |
Doña Ana County, New Mexico, United States | OpenAI (Oracle-operated) | Under construction | 2.2 GW facility power | 0 MW facility power | Grid; facility-power figure. | Foundation work under way; completion projected Q4 2028. |
Lordstown, Ohio, United States | OpenAI (SoftBank-owned hardware) | Announced | not stated facility power | 0 MW facility power | Not stated. | Land cleared; no large-scale construction visible; timing unknown. |
Milam County, Texas, United States | OpenAI (SoftBank-owned hardware) | Under construction | 1.2 GW facility power | 0 MW facility power | SB Energy's own generation and grid; a "fast-build" design. | Building delivery by October 2026 per filings; completion projected Q4 2028. |
Port Washington, Wisconsin, United States | OpenAI (Oracle-operated) | Under construction | 1.3 GW facility power | 0 MW facility power | Grid (We Energies); facility-power figure. | Foundation work under way; completion projected Q4 2028. |
Saline Township, Michigan, United States | OpenAI (Oracle-operated) | Under construction | 1.4 GW facility power | 0 MW facility power | DTE Energy supplies the grid connection. | Foundation work under way for the first building; completion projected Q4 2028. |
Shackelford County, Texas, United States | OpenAI (Oracle-operated) | Under construction | 2 GW facility power | 0 MW facility power | Grid (ERCOT); facility-power figure. | Roofing under way; first building delivery late 2026; completion projected Q4 2028. |
Abu Dhabi, United Arab Emirates | OpenAI · G42 | Under construction | 5 GW basis not stated | not stated basis not stated | Not stated for the campus; the UAE grid is gas and nuclear (Barakah) backed. | First 200 MW of a 1 GW cluster due in 2026; the rest of the 1 GW and the 5 GW campus have no confirmed dates. |
Montréal and Québec City, Canada | Multi-tenant | Operating | 178 MW basis not stated | 178 MW basis not stated | Hydro-Québec. | Operational. |
Memphis, Tennessee / Southaven, Mississippi, United States | xAI (SpaceX) | Operating | 2 GW IT power | 1 GW basis not stated | Largely off-grid: on-site gas turbines and batteries; TVA had not committed firm grid capacity as of the sources read. | Crossed ~1 GW in 2026; 440,000 GB300 GPUs reported in use by late September 2026 with a further 660,000 expected by year-end. |
Energy assets and grid rules
| Asset | Kind | Serves | Capacity | Timing |
|---|---|---|---|---|
Londonderry Township, Pennsylvania, United States | Nuclear restart | Microsoft — 20-year power purchase agreement | 835 MW | Constellation targets 2027, "ahead of schedule"; the NRC issued its environmental finding of no significant impact in late September 2026, with exemption and licence-amendment decisions still pending. |
Covert, Michigan, United States | Nuclear restart | Michigan grid (Wolverine Power / Hoosier Energy offtake); the first US restart of a closed reactor | 800 MW | Holtec targets restart in 2026 after two missed dates; the NRC is reviewing a licence amendment filed after a fuel-loading incident paused some work. |
Salem Township, Pennsylvania, United States | Existing nuclear (PPA) | Amazon Web Services — the adjacent campus and other Pennsylvania sites | 1.9 GW | 840–1,200 MW in 2029, 1,680–1,920 MW by 2032 at the latest. |
Oak Harbor and Perry, Ohio; Shippingport, Pennsylvania, United States | Existing nuclear (PPA) | Meta — Prometheus and the PJM campuses | 2.6 GW | Purchases begin late 2026; uprate capacity added through 2034. |
Piketon area, Ohio, United States | New nuclear / SMR | Meta | 1.2 GW | By 2035 across the Meta nuclear set; no unit dates stated. |
Sites for Meta-funded units not disclosed, United States | New nuclear / SMR | Meta — up to eight Natrium units, rights to output | 690 MW | By 2035. |
Oak Ridge, Tennessee, United States | New nuclear / SMR | Google — clean-energy attributes for its Tennessee and Alabama data centers | 50 MW | Operations scheduled to begin 2030. |
Richland, Washington, United States | New nuclear / SMR | Amazon-funded; Pacific Northwest data centers | 320 MW | Targeting construction by 2030. |
Richland Parish, Louisiana, United States | Gas (on-site or new plant) | Meta Hyperion | not stated | First Hyperion phase 2028. |
New Albany, Ohio, United States | Gas (on-site or new plant) | Meta Prometheus | not stated | With the 2026 cluster. |
Southaven, Mississippi, United States | Gas (on-site or new plant) | xAI Colossus 2 | not stated | A 150 MW grid build-out not scheduled to energise until late 2026. |
Homer City, Pennsylvania, United States | Gas (on-site or new plant) | The Homer City energy campus (tenant not yet named) | 4.5 GW | Construction from 2025. |
Southeastern United States (2,500 acres; state not stated), United States | Gas (on-site or new plant) | Seeking an AI tenant | 1.2 GW | Planned. |
Narvik, Norway | Renewable | The Narvik AI gigafactory | 230 MW | With the campus. |
Dublin, Ireland | Grid connection policy | Every new Dublin-area data center | not stated | In force from 2026 applications. |
Amsterdam, Netherlands | Grid connection policy | Hyperscale projects in the Amsterdam region | not stated | In force. |
Singapore, Singapore | Grid connection policy | New data centers in Singapore | not stated | Rolling. |
Evidence review queue and change history
Public editorial quality queue for this curated register. Review flags identify missing evidence, not proof a project is late or incorrect. Source revisions are reviewed in GitHub before publication.
- Stargate Abilene: Historical evidence requires current status check
- Stargate Shackelford County: Historical evidence requires current status check
- Stargate Doña Ana (Project Jupiter): Historical evidence requires current status check
- Stargate Milam County: Historical evidence requires current status check
- Stargate Port Washington (Lighthouse): Historical evidence requires current status check
- Stargate Saline Township (The Barn): Historical evidence requires current status check
- Stargate Lordstown: Historical evidence requires current status check; Epoch reports less than 300 MW, not an exact 300 MW. The exact capacity is withheld pending clarification; the source describes manufacturing activity and limited campus construction.
- Meta Hyperion: Metric-level verification not recorded; Full-build power basis not stated
- Meta Prometheus: Metric-level verification not recorded; Full-build power basis not stated
- Meta Lebanon: Metric-level verification not recorded; Full-build power basis not stated
- xAI Colossus 2: Metric-level verification not recorded; Operating power basis not confirmed
- Amazon Project Rainier: Metric-level verification not recorded; Full-build power basis not stated
- Microsoft Fairwater Wisconsin: Metric-level verification not recorded; Full-build power basis not stated
- Microsoft Fairwater Atlanta: Metric-level verification not recorded; Full-build power basis not stated
- Google Wilbarger County: Metric-level verification not recorded; Full-build power basis not stated
- Homer City Energy Campus: Metric-level verification not recorded; Full-build power basis not stated
- Stargate UAE (UAE–US AI Campus): Metric-level verification not recorded; Full-build power basis not stated
- Humain AI Data Centers: Metric-level verification not recorded; Full-build power basis not stated
- Narvik AI gigafactory (ex-Stargate Norway): Metric-level verification not recorded; Full-build power basis not stated
- Campus AI (MGX · Mistral) Île-de-France: Metric-level verification not recorded; Full-build power basis not stated
- Digital Realty UK AI mega-campus: Metric-level verification not recorded; Full-build power basis not stated
- Google AI Hub Visakhapatnam: Metric-level verification not recorded; Full-build power basis not stated
- Reliance–Meta Jamnagar: Metric-level verification not recorded; Full-build power basis not stated
- Microsoft India South Central region: Metric-level verification not recorded; Full-build power basis not stated; The legacy mid-2026 go-live target has elapsed while the record remains under construction. Obtain a dated commissioning update; do not infer completion.
- SoftBank Tomakomai AI data center: Metric-level verification not recorded; Full-build power basis not stated
- Data Center Valley, Ekibastuz: Metric-level verification not recorded; Full-build power basis not stated
- Vantage Québec expansion: Metric-level verification not recorded; Full-build power basis not stated; Operating power basis not confirmed
- Equinix SP7 São Paulo: Metric-level verification not recorded; Full-build power basis not stated
- AWS Peru region: Metric-level verification not recorded; Full-build power basis not stated
Reviewed editorial changes
- 2026-10-18 · capacity evidence
Before: Generic source date and reported capacity
After: Explicit third-party estimate, publication/effective/review dates and metric bindings
Epoch explains its facility-power estimates and April revision.
Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18 - 2026-10-18 · capacityMw
Before: 300 MW exact
After: Exact value unknown; source upper bound <300 MW retained in notes
Do not convert a bound to an exact measurement.
Elliot Stewart and Ben Cottier / Epoch AI — Stargate (CC BY) · Third-party estimatePublished: 2026-04-17 · Effective: 2026-04-23 · Source checked: 2026-10-18 · Next review: 2026-11-18 - 2026-10-18 · editorial interpretation
Before: Described as running on new gas
After: Under construction with gas-backed supply planned
Align interpretation with the record's project phase.
Demand and constraints
How much power, and what is in the way
Global data centre electricity, 2025
485 TWh
About 1.5% of world electricity, before most of the campuses on this map draw power.
IEA — Key Questions on Energy and AI (2026), executive summaryPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-01
Global data centre electricity, 2030 (IEA)
~950 TWh, ~3% of demand
A doubling in five years; AI-optimised data centres more than quadruple over the same period.
IEA — Key Questions on Energy and AI (2026), executive summaryPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-01
US increase to 2030 (IEA)
up to +240 TWh, +130% on 2024
The US and China account for most of the growth; the US is where the grid fight is.
DCD — IEA: data center energy consumption set to double by 2030Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-04-10
IT capacity under construction, end-Sept 2025 (BloombergNEF)
23.1 GW across 831 sites; 15.9 GW in the US
A reported construction pipeline with its own coverage and IT-power basis; not directly comparable with this selected campus register.
Data Center Knowledge — AI-first hyperscalers: 2026's sprint meets the power bottleneckPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-15
Of ~16 GW slated for 2026 completion (Sightline)
30–50% slips to 2027 or later
Power procurement, transformers and permits, not concrete, set the pace.
Archdesk — AI data center construction 2026: capex, cost per MW, delaysPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-06-01
GE Vernova gas turbine backlog, end-Q2 2026
116 GW; new orders deliver in 2031
Reported turbine lead times can constrain projects planning gas generation; availability varies by equipment and contract.
Utility Dive — GE Vernova gas turbine backlog climbs to 116 GWPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-23
Capital
Who is paying, and how
Top-5 hyperscaler capex, 2026 (CreditSights)
$602 billion, +36%
Most of it is data centers and the chips inside them.
Data Center Knowledge — hyperscalers in 2026Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-15
US data center construction, August 2026 (Census, annual rate, preliminary)
$84.95 billion, +73% year on year
Shells and power only — servers, racks, plants and transmission are counted elsewhere.
Axis Intelligence — data center construction spending: Census dataPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-02
US data center investment, 2025 (S&P Global)
$63.35 billion; private equity 72%
This is a transaction-market measure; it does not establish the accounting treatment of any tenant's commitments.
S&P Global — private equity sends US data center deals to a 5-year highPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-15
Largest private digital-infrastructure deal
Aligned Data Centers, $40 billion
AIP, BlackRock's GIP and MGX bought a developer, not a tenant — the shell is now the asset class.
Aligned Data Centers — acquisition closesPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01
Stargate US sites by 2029 (Epoch AI)
>9 GW across seven sites
A reported development pipeline, including future phases, rather than delivered operating capacity.
Epoch AI — where the US Stargate sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23
US data center industry contribution to government revenue (PwC)
$66.2bn (2017) → $162.7bn (2023)
The fiscal case the industry makes; set it beside the incentives below.
Georgia Tech — who benefits? (citing PwC)Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09
Communities
What a town gets, and what it gives up
Reported measurements, estimates and commitments. Their source populations and dates differ; they are not universal forecasts.
A typical site (Georgia Tech)
~1,500 to build, under 200 to run
The jobs are in the construction phase; permanent headcount is small relative to the power draw.
Georgia Tech — Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09
Local electricity price after a large facility enters (Georgia Tech)
about +5%
Where the effect can be measured cleanly it is real and modest; the PJM figure below is the system-wide version.
Georgia Tech — Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09
PJM customer price increases attributed mainly to data center demand (market monitor)
$23 billion through 2028
A reported attribution in PJM; it does not establish the effect on every customer bill or other regions.
Fortune — data centers have already hiked electricity prices by $23 billionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-14
US data center water use (DOE)
~17 billion gallons (2024) → ~80 billion by 2028
Cooling water is the second grievance; outside-air and closed-loop designs are the industry's answer.
Wikipedia — AI data center (citing DOE via The Guardian)Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15
Ohio data center tax exemptions, 2025
$1.6 billion, 11× the projection
Incentives scale with the capex they were written for, not the one that arrived.
Georgia Tech — Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09
Loudoun County, Virginia property taxes over a decade
cut ~30%, on ~250 data centers
A reported local fiscal outcome; incentives, tax structures and infrastructure costs differ elsewhere.
Georgia Tech — Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09
States offering data center tax incentives (NCSL)
at least 38
Incentive competition is national; at least 10 states forgo more than $100 million a year (Good Jobs First).
Georgia Tech — Data centers are booming. Who benefits?Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-09
Backlash and policy
Pauses, directives, lawsuits and connection rules
Newest first. A count is a count by the outlet named, not Koko's.
- Directive TexasGovernor Abbott's directive to bar data centers from taking water or grid power communities need; he says it halted up to 1,800 projects (his own figure). (The Daily Signal — data center backlash brings thousands of projects to a haltPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-08-23)
- Moratorium New YorkExecutive order creating the first statewide moratorium on new hyperscale data centers; Pennsylvania, Michigan and South Carolina considering pauses. (Resilience — the data center backlash that's uniting AmericaPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-23)
- Measured United StatesMore than 300 cities, towns and counties with bans or moratoriums on hyperscale data centers (a count by The Information). (TIME — Community backlash to AI data centers is growing across the U.S.Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-22)
- Measured United States75 major projects worth more than $130 billion delayed or cancelled in the first three months of 2026, in part due to organised local opposition. (TIME — Community backlash to AI data centers is growing across the U.S.Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-22)
- Moratorium Seattle · DenverSeattle became the largest US city with a data center moratorium; Denver's council unanimously approved a one-year pause while it drafts rules. (Stateline — more cities are pressing pause on data centersPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-28)
- Rejection Sangamon County, IllinoisA proposed six-month moratorium failed 5–3 in committee — moratoria do not always pass. (Stateline — more cities are pressing pausePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-28)
- Lawsuit Memphis / SouthavenNAACP, with SELC and Earthjustice, sued xAI alleging Colossus 2 gas turbines operate without Clean Air Act permits. (NAACP v. xAIPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-15)
- Connection policy IrelandCRU's Large Energy User Connection Policy ended the de facto Dublin moratorium: on-site dispatchable generation or storage matching import capacity, 80% additional Irish renewables over six years. (Environment+Energy Leader — Ireland's grid now asks which data centers are crediblePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-20)
- Rejection Saline Township, MichiganThe township rejected the Stargate site; the developers sued and acquired the land in a settlement. (Wikipedia — AI data center (Saline Township)Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15)
- Moratorium Amsterdam regionHyperscale facilities over 10 hectares and 70 MW prohibited since January 2024 without a pre-2022 permit application. (DCD — the ongoing impact of Amsterdam's moratoriumPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-06-01)
Who enables it
The chain, end to end
Anchors, chips, builders, power, equipment and capital. A row with a figure links its source; a row without one carries its role only. Listed companies open on the company hub.
Anchor tenants and labs
OpenAI
Stargate's tenant across seven US sites and the UAE; the demand signal behind Oracle, Crusoe, Vantage and SoftBank's builds.
Epoch AI projects the seven US Stargate sites at more than 9 GW by 2029. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
Builds its own campuses (Hyperion, Prometheus, Lebanon) and signs the largest corporate nuclear deals.
Up to 6.6 GW of nuclear agreements with Vistra, TerraPower and Oklo (January 2026). (Axios — Meta nuclear dealsPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-09)
Fairwater in Wisconsin and Atlanta; took over the Narvik capacity OpenAI dropped.
A 20-year PPA for the Crane (Three Mile Island) restart. (NRC — Crane restart environmental findingPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-09-30)
Project Rainier for Anthropic; the largest nuclear PPA with Talen; funds X-energy's Cascade reactors.
1,920 MW from Susquehanna through 2042. (Talen Energy — expanded Amazon agreementPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-06-11)
Visakhapatnam, Texas and Minnesota campuses; the first Gen IV reactor PPA via TVA.
$15 billion over 2026–2030 for the 1 GW Visakhapatnam hub. (Google India blog — AI HubPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-28)
xAI (SpaceX)
Colossus in Memphis, built largely off-grid on gas turbines.
~1 GW live, 2 GW targeted. (Techzine — xAI expands Colossus to 2 GWPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-06-01)
Anthropic
Rainier's tenant on AWS; Fluidstack sites in New York and Texas announced November 2025.
$50 billion of Fluidstack sites announced. (Wikipedia — AI data centerPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15)
G42 · MGX
Abu Dhabi's AI champion and its investment arm: Stargate UAE, Campus AI France, the Aligned consortium.
Co-acquirer of Aligned Data Centers at a $40 billion enterprise value. (Aligned Data Centers — AIP, MGX and BlackRock's GIP close $40B acquisitionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01)
Chips and compute
GB200/GB300 and Rubin GPUs in nearly every campus here; an equity partner in Stargate UAE and the Aligned consortium.
Abilene is built for more than 450,000 GB200 GPUs; Narvik takes 30,000 Rubin GPUs in 2027. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
Humain's accelerator partner; an OpenAI supply agreement.
Role only — no figure read for this row.
Amazon's own training chip; Rainier runs ~500,000 Trainium2.
Rainier is Trainium-only, not NVIDIA. (Wikipedia — AI data center (Rainier)Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15)
Custom accelerators and networking for the hyperscalers; an OpenAI custom-chip partner.
Role only — no figure read for this row.
Groq
Inference silicon for Aramco Digital's announced 500 MW Saudi facility.
Role only — no figure read for this row.
Developers, builders and operators
Crusoe
Developer of Stargate Abilene.
357 full-time jobs committed at Abilene once construction ends. (Programs.com — data center employment statisticsPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-08-01)
Vantage Data Centers
Developer of the Shackelford County and Port Washington Stargate sites; Québec campus.
Two Stargate sites totalling 3.3 GW projected. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
STACK Infrastructure
Developer of Project Jupiter, Doña Ana County.
2.2 GW projected, Q4 2028. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
Related Digital
Developer of The Barn, Saline Township.
1.4 GW projected after litigation and a settlement with the township. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
SB Energy (SoftBank)
Developer and power provider for the Milam County Stargate site.
A "fast-build" site with SoftBank-owned hardware. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
Khazna Data Centers
Builder of the Stargate UAE cluster for G42.
First 200 MW due in 2026. (Gulf News — Stargate UAE first phasePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-10)
Nscale · Aker
Joint-venture developer of the Narvik gigafactory.
Microsoft contracted 30,000 Rubin GPUs there for 2027. (DCD — Microsoft contracts 30,000 Rubin GPUs from NscalePublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-15)
Aligned Data Centers
Hyperscale developer bought by AIP, GIP and MGX.
$40 billion enterprise value plus $5 billion of committed growth capital. (Aligned Data Centers — AIP, MGX and BlackRock's GIP close $40B acquisitionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01)
Operates five of the seven US Stargate sites and owns their hardware; OpenAI's largest compute supplier.
Owns the hardware at Abilene, Shackelford, Doña Ana, Port Washington and Saline. (Epoch AI — OpenAI Stargate: where the US sites standPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-04-23)
The two listed colocation majors; smaller AI-ready builds worldwide.
Role only — no figure read for this row.
AdaniConneX · Nxtra (Airtel)
Build the Visakhapatnam AI hub for Google.
Role only — no figure read for this row.
Power: generation, fuel and grid
Largest US nuclear operator; restarting Crane for Microsoft.
835 MW restart targeted 2027 with a $1 billion DOE loan. (Constellation — Crane one year laterPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-09-19)
Ohio and Pennsylvania nuclear output and uprates sold to Meta.
2,176 MW plus 433 MW of uprates under a 20-year PPA. (ANS — the Meta–Vistra dealPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-01-12)
Susquehanna output to Amazon.
About $18 billion of revenue expected over the contract. (Talen Energy — expanded Amazon agreementPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-06-11)
Holtec
Restarting Palisades; SMR developer; filed for an IPO in 2026.
Restart targeted 2026, ahead of a March 2027 counterparty date. (Holtec — Form S-1Published: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-08-15)
Advanced-reactor developer; a 1.2 GW campus for Meta in Ohio.
Role only — no figure read for this row.
TerraPower
Natrium sodium fast reactors; up to eight units funded by Meta.
Role only — no figure read for this row.
Kairos Power
Hermes 2 molten-salt reactor for TVA and Google.
50 MW from 2030. (Kairos Power — Google, Kairos, TVAPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-08-18)
X-energy · Energy Northwest
Four Xe-100 reactors in Washington, Amazon-funded.
Role only — no figure read for this row.
The only NRC-certified SMR design; shares down 53% year to date by October 2026.
Role only — no figure read for this row.
Builds three gas plants for Hyperion in Louisiana.
Role only — no figure read for this row.
Behind-the-meter gas for Meta Prometheus.
Role only — no figure read for this row.
Gas supply to the Homer City campus.
Role only — no figure read for this row.
Gas-with-capture project with ExxonMobil; the Duane Arnold restart.
Role only — no figure read for this row.
Tennessee Valley Authority
Grid for Colossus and the Hermes 2 offtaker.
Role only — no figure read for this row.
Turbines, transformers, cooling
Heavy-duty gas turbines — the pacing item for behind-the-meter power.
Backlog 116 GW at end-Q2 2026; new orders deliver in 2031; lead times "directionally about three years"; data centers ~20% of the book. (Utility Dive — GE Vernova gas turbine backlog climbs to 116 GWPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-07-23)
Siemens Energy
Gas turbines and grid equipment; the other Western turbine supplier.
Role only — no figure read for this row.
Hitachi Energy
Large power transformers — the other long-lead item.
Role only — no figure read for this row.
Fuel cells for on-site power.
Role only — no figure read for this row.
Vertiv · Schneider Electric · Eaton
Liquid cooling, power distribution and switchgear inside the hall.
Role only — no figure read for this row.
Foxconn
Rack and server integration; JV partner at Lordstown; Fairwater sits on its former Wisconsin site.
Role only — no figure read for this row.
Capital: funds, SPVs and lenders
Financed Hyperion through a joint-venture SPV; a Stargate Abilene investor.
Hyperion JV reported at ~$27 billion of development. (Wikipedia — Hyperion Data CenterPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-10-15)
AI Infrastructure Partnership (AIP)
BlackRock, Microsoft, MGX, NVIDIA and xAI's infrastructure fund.
Aligned was its first investment; a $30 billion equity target supporting up to $100 billion with debt. (Aligned Data Centers — AIP, MGX and BlackRock's GIP close $40B acquisitionPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-03-01)
BlackRock · Global Infrastructure Partners
Co-acquirer of Aligned.
Role only — no figure read for this row.
SoftBank Group
Stargate's financing partner; owns the Milam County and Lordstown hardware.
Role only — no figure read for this row.
Macquarie Asset Management
Sold Aligned to the consortium.
Role only — no figure read for this row.
The private-capital owners of QTS and the European and Asian colocation platforms.
Private equity was 72% of the $63.35 billion invested in US data centers in 2025. (S&P Global — private equity sends US data center deals to a 5-year highPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2026-05-15)
Bpifrance
French state investor in the Campus AI project.
Role only — no figure read for this row.
US Department of Energy loan office
Restart lender.
$1 billion to Constellation for Crane. (Constellation — Crane one year laterPublished: not distinguished · Effective: not specified · Source checked: not recorded · Next review: not scheduled · Legacy source/access date: 2025-09-19)
Koko's PoV
Six reads of the map
Koko's view. Each rests on the figures above and adds no number of its own.
1.Power delivery belongs in the AI capacity decision.
The Crane restart record describes a disputed connection timetable; the equipment figures describe long lead times. These examples suggest delivery risk, but do not establish that every on-time campus has its own generation.
For: CFOs and technology leaders: verify a provider's delivery milestones and contingency capacity before committing spend.
2.Community acceptance depends on who bears the costs and receives the benefits.
The community register includes reported rate effects, water concerns, job commitments and tax incentives. Their relative importance varies by jurisdiction; a local study is not a universal forecast.
For: Developers and advisers: test cost allocation and community commitments against the local evidence.
3.Financing terms can matter as much as announced campus size.
The Hyperion joint venture and Aligned acquisition show different ways to finance infrastructure. A JV alone does not establish off-balance-sheet accounting or transfer all risk from a tenant.
For: Treasurers and investors: review lease obligations, guarantees, consolidation judgments and completion conditions.
4.Separate construction employment from lasting local benefits.
Abilene and Hyperion report different construction and permanent commitments. Local tax receipts also depend on incentives and ownership terms, so one county's outcome should not be generalized.
For: Local governments and advisers: reconcile jobs, incentive costs and fiscal benefits over the project lifecycle.
5.Power arrangements have different delivery and emissions profiles.
Colossus has reported gas generation; Hyperion is under construction with gas-backed supply planned. Nuclear restarts, existing-plant PPAs and new reactors have different milestones. A contract does not prove physical supply or an achieved carbon outcome.
For: Energy and sustainability leads: check asset status, connection evidence, hourly supply and accounting boundaries.
6.Infrastructure creates several distinct advisory needs.
The register points to procurement, project finance, permitting, community agreements, reporting and supply-chain questions. These are potential engagements, not evidence of a quantified market or a mandate.
For: Partner / MD: connect a specific client exposure to a sourced development and a concrete diligence question.
Opportunities · directional
Where the work is
Koko's reading of where the demand lands, for companies and for professional-services firms. Directional, not a sized market.
For companies
AI capacity sourcing: own, colocate or rent
Signal: Hyperscaler capex at $602 billion and 30–50% of 2026 completions slipping.
A capacity plan that prices cloud, colocation and dedicated builds against the model portfolio, with power as the binding constraint.
On Koko: AI Stack Economics
Energy procurement for AI load
Signal: Nuclear PPAs from 2027, turbines sold out to 2031, Ireland's self-supply rule.
PPA and behind-the-meter options, interconnection timing, and what the carbon ledger says to investors.
Sovereign and regional AI capacity
Signal: Stargate UAE, Narvik, Visakhapatnam, Campus AI France, Ekibastuz.
Data residency and export-control-aware placement for multinational AI workloads.
On Koko: TMT Daily
Supplier and customer exposure to the build-out
Signal: GE Vernova, Vistra, Constellation, Talen, Oracle and the colocation majors each carry a sourced hook here.
Read the operators and enablers on this page through their own filings.
On Koko: Company hub
For professional-services firms
Site selection and incentive negotiation
Signal: At least 38 states with incentives; Ohio's $1.6 billion overrun; 300+ local pauses.
Incentive modelling, abatement and sales-tax exemption structuring, and the community benefit agreement that gets a vote through.
On Koko: Transform suite
Power procurement and rate-case support
Signal: Entergy's three plants for one customer; PJM's $23 billion; CRU's self-supply rule.
PPA structuring, cost-allocation testimony, interconnection strategy and the tariff work utilities now run for single customers.
On Koko: Transform suite
Project finance, SPVs and transaction advisory
Signal: Blue Owl–Meta, Aligned at $40 billion, private equity at 72% of deals.
JV and SPV structuring, lease accounting, debt capacity, buy-side diligence on shells and power.
On Koko: Accounting & Tax Watch
Energy, water and emissions assurance
Signal: DOE water figures, EU reporting rules, the Colossus permit suit.
Metered reporting, PUE and water assurance, and the controls behind the sustainability claims in an offering memorandum.
On Koko: Internal Control Screen
Supply chain and construction cost control
Signal: Turbines on a three-year lead, transformers behind them, $85 billion annual construction pace.
Procurement strategy for long-lead equipment, schedule risk, and owner's-engineer cost control.
On Koko: Process Architecture Studio
Related news
The build-out in Koko's corpus
Stories about data centers, power deals and the grid from the sources Koko reads every day.
- Microsoft Debuts New Homegrown AI Chip, Plans to Deploy Multiple Gigawatts Next Year
External (via citation)
- Microsoft Prepares to Put Gigawatts of Its Chips in Data Centers
External (via citation)
Learn
New to this?
How a Data Center Gets Built walks the six stages from site to operation, who is involved at each, how long they take and what stops them, with the vocabulary in plain words. Ask the map a question in Ask Koko.